HomeMy WebLinkAboutInterwest Construction, Inc., Change Order No. 4 - 042522 ,
• ` .-r-----vim.. --v—. •
Sheet 1 of 2 DEPARTMENT OF PUBLIC WORKS Change 4
Date: 4/18/2022 CHANGE ORDER Order No.
Ordered by County Engineer under terms of
Qseetion I-04,4 of the Standard Specifications
Contract No.
Change proposed by Contractor 'I'o:
Interwest Construction,Inc.
Endorsed by: Interwest Construction,Inc. 609 North Hill Blvd.
CuniracrorlineNanre Burlington,WA.98233
tkitz .
qdyi-- 0/
gnature Dare
I bee- e
Title
Consent given by Surely:(when regniret0 Project Title
SR 116 and Cedar Ave.Ned:Rilte Improvements
By: Project No.1802057
Attorney-in-fact Date 11
You are ordered to perform the following described work upon receipt of an approved copy of this change order:
Item 3 Removal of Structures and Obstructions
This change order adds additional work to the existing item "Item 53 Removal of Structures and Obstructions"per
Standard Specification 1-04.4. This change order provides for removing two existing utility poles that conflict with
the proposed concrete sidewalk location. The poles are located on the west side of Cedar Ave.at the 1st street
intersection and at the 2nd street intersection.
Estimated cost is:$1,075.02
Change in Contract Time:0.5 additional Working Days
Total Change Order 4 Summary
$1,075.02 Item 53 Removal of Structures and Obstructions
$1,075.02 Total Estimated Net Cost Change
All work materials and measurement to be in accordance with the provisions of the standard specifications and
special provisions for the type of construction involved.
•
ORIGINAL CURRI:N'I ESTIMATED ESTIMATED
CONTRACT CONTRACT NET CHANGE CONTRAC'I'TOTAL
AMOUNT AMOUNT THIS ORDER AFTER CHANGE
$573,723.61 $582,598,22 $1,075.02 $583,673.24
i ORIGINAL CURRENT CONTRACT TIME NEW CONTRACT
CONTRACT TIME CONTRACT TIME CHANGE(Add/Del) TIME
' 75 Working Days 79 Working Days 0.5 Working Days 79.5 Working days
APPROVAL RECOMMENDED APPR VAt.RI;COMME ti1J
EI
411 41614,- ------. of --/e3—7-7--- ‘1.(6.p.-- .
Rroje Maltage, Date County Engineer Date
APPROVAL R,iCOMMENDCD APPR •D
gi„,-- ,.
---(.......___' (7/72.s-7.22_, .
I�zv
Engineering Ser ces Manager Date Chair,Jefferson County Commissioners Date
1
i
o ( 1 C. N 0
0
o ( � '3Iz¢ n O N S
f i
Gal 69 64
k
t
I
I 1F ! of 0 o1
w'o p o N 0
z, -.1 ell '.0 0o F
<
I ; I v;(.0 fos 771
ci l{
I I j IH j
w!� F o o o U
IZ
,7 i O t Vo cn o F"
1� 0 o —;1 Z
i ;
F,1 W 0 O O1
L�}.-: U h' V1 ma`s
1 Z , S S hi —
i I t I p_, 00 00 00,
6 (~
�i 0
i I .. 691 0 01 W
ca
zi d 1;61€7'v) 00 0 01
1 I
C..) lUi 9
,
1 'v {F O p of
`ZI z o; o of
jF Q;� o: o of
l.(f_ `D ooi
i
69; N kill
69 941
r i --
gUI H
lo, ,
i F i F, tr1 V1
F v.:
1 I,41u; Q o" O �i
1it ; i W
3
i I d
y C. O p
c 000, 000 000;
0 IHI j° 0! 0 03
'ao I"" I �' €
IN £ iz'H;n
UO °4 w ' v) �?¢ 1 a' 00
0r0i ;
ZOi � ice, j � 1
LL,jW i 1
r41i x :0 2
M 1 Zi B
Gil W
-5t€10.aQi� !0 ;�i � O � O
`W iUi 44, u, W V
G ? l ill as1 I
i j U I a l 0 0 0 0
I
i
( o I
n. , ..a i
1 `wel to Q W; g <I
v i o; z E-" N F
1 I '—, OI
C7
N ; 1 0
z
,
y
,....,1�1 y 9 IC( r►�/I M1 1
{V]( IC) ; i 1 W 5
Department of Public Works
0 Consent Agenda
Page 1 of 1
Jefferson County
Board of Commissioners
Agenda Request
To: Board of Commissioners
Mark McCauley, County Administrator
From: Monte Reinders, P.E., Public Works Director/County Engineer ie
Agenda Date: April 25, 2022
Subject: Change Orders No. 2, 3, and 4, for SR 116 and Cedar Avenue
Pedestrian - Bike Improvements Project, Project No. 1802057,
County Road No. 637109, WSDOT Project No. HLP-SR19(006)
Statement of Issue: Change Orders No. 2, 3, and 4 with Interwest Construction, Inc.
of Burlington, Washington.
Analysis/Strategic Goals/Pro's Et Con's: These change orders consist of:
Change Order No. 2: Substitution of Crushed Surfacing Top Course for all occurrences
of Crushed Surfacing Base Course in order to improve the constructability methods for
this project.
Change Order No. 3: Changed condition for constructing concrete sidewalk adjacent
to the installed Pedestrian Light Poles along Cedar Avenue.
Change Order No. 4: Removal of 2 utility poles that conflict with the proposed
concrete sidewalk.
Fiscal Impact/Cost Benefit Analysis: Change Order No. 2 adds no ($0.00) additional
cost or Working Days. Change Order No. 3 adds $6,266.40 and 2 Working Days.
Change Order No. 4 adds $1,075.02 and % Working Day. The total cost increase for
all 3 change orders is $7,341.42. This project is funded at 100% by a WSDOT Safe
Route to School Program (State) grant.
Recommendation: Public Works recommends that the Board authorize Change Orders
No. 2, 3, and 4 with Interwest Construction, Inc., and return two originals of each to
Public Works for further processing.
Department Contact: John Wayand, Project Manager, 385-9377.
Rev!aCounty!nistrator
By:
Mar Date