STATE OF WASHINGTON
County of Jefferson
IN THE MATTER OF
ACCEPTING BID FOR CONSTRUCTING
THE H. 1. CARROLL PARK, PHASE ONE
COUNTY PROJECT, HJ0594
}
}
}
}
RESOLUTION NO. 94-97
WHEREAS, Jefferson County Board of Commissioners on July 14, 1997 called for
bids for the above mentioned project, and;
WHEREAS, due notice of the call for bids was given as required by law, and;
WHEREAS, THREE bids were received and opened during public session on
August 4, 1997 at 2:45 p.m., as shown in the attached bid tabulation, and;
WHEREAS, it is in the best interest of the people of Jefferson County to select the
most responsive of the THREE acceptable bids, now therefore,
IT IS HEREBY RESOLVED, that the best and most responsive bid was submitted
by SETON CONSTRUCTION, INc., for a total base bid amount of $308,517.39 and that this
bid be accepted and
IT IS FURTHER RESOLVED, that the specifications and contract documents in
their entirety as included in the bid package, are part of this bid acceptance,
APPROVED AND ADOPTED thi s LAy of ¡f.-~
SEAL:
. ..""" . ~ '.
,.,.,: . ~ 'i v.... -',
, " ,
it. ,,--;.\,,'Jo',\
.' ',' (-4.~ 1- ..
':. 'J. '-......~,¡,."'..
.l..~"t", '.1','"
¡ <':' #' .¡i'.. ' Xc " \ . ,
\:~!k.'\ ""::1' :::1
I .... ".;l/... ,"""'" . .,' (
'.",..~..,,' '.',/
\ ",-:: > ~ J ~j ',: ...-
\. ft '................ '-; ,
',' ,," ~
"'.... . ')' ,-
""-~. _.. ..'
A TTES d ~ 0.. !1tJ ~
Lorna L. Delaney ð
Clerk of the Board
~ 1-~4
Daniel Harpole, Memb r
~VOl
23 ;A~;559
.~..
H.J. Carrol Park
Remaining Budget - 1997
Revenue: Aug. 1, 1997
Remaining Cash $206,500
Open Space ACQ. Fund $73,000
Earned Interest $4,000
Estmated Interest -
8/97 - 12/97 $4,000
Total Amount Available $287,500
Expenditures: (Aug. - Dec.)
July Bills Paid in Aug. Est. $3,000
Staff Salary - P.M. 400 Hrs. @ $22.80 $9,120
Staff Salary - Insp. 240 Hrs.@ $24.75 $5,940
Public Outreach Est. $7,000
Consultants:
Remaining Design Est. $11,000
Material Testing Est. $6,500
Items N.I.C.:
Fencina So. Bndry. 900 L.F. @ $9.00 $8,100
Electrical Service Est. $11,000
Water Service Est. $22,110
Sub Total Expenditures $83,770
Amount Available For Contract:
$203,730
Low Base Bid Amount:
$308,517.39
Budget Amount Needed:
$104,787.39
~VOL
23 '!,~.:560
Page 1