HomeMy WebLinkAboutInterwest Construction, Inc., Change Order No. 5 - 062722 .)-7. ??___ ��-. y JEFFERSON COUNTY Sheet of 2 DEPARTMENT OF PUBLIC WORKS Change j Date: 4/22/2022 CHANGE ORDER Order No. S Ordered by County Engineer under terms of ❑X Section 1-04.4 of the Standard Specifications Contract No, OCitange proposed by Contractor To: Interwest Construction,Inc. Endorsed by: nterwestF ConstructiNameon,Inc. 609 North Hill Blvd. n 14/2 '51 Z.-L--' ! Burlington,WA.98233 onrractor irm signature ate Z.,V fee YF`�r�jtA'�' � Title -= Consent given by Surety:(when required) Project Title �� SR 116 and Cedar Ave.Pcd:hike Improvements By: Project No.1802057 • Attorney-in-fact Date You are ordered to perform the following described work upon receipt of an approved copy of this change order: n Item 53 Removal of Cement Conc.Driveway Entrance and Traffic Curb&Gutter This change order adds one new item"Item 53 Removal of Cement Conc.Driveway Entrance and Traffic Curb& G_—" Gutter"per Standard Specification 1-04.4. This change order provides for removing 38 LF of cement concrete "...1,..., driveway entrance and 58 LF of cement conc.traffic curb&gutter at the 1ST Street entrance on Cedar Ave. This change order will remove the 2"high gutter lip that is not ADA compliant and rectify the contractor's omission of Detectable Warning Surfaces(DWS). The cement concrete driveway entrance and curb&gutter will be replaced with 1/2"high gutter lip and DWS that are ADA compliant. LT7 Estimated cost is:$2,742.60,L.S. Change In Contract Time:0.5 additional Working Days Total Change Order 5 Summary $2,742.60 Item 53 Removal of Cement Conc. Driveway Entrance and Traffic Curb& Gutter $2,742.60 Total Estimated Net Cost Change All work materials and measurement to be in accordance with the provisions of the standard specifications and special provisions for the type of construction involved. ORIGINAL CURRENT ESTI MATED ESTIMATED CONTRACT CONTRACT NET CHANGE CONTRACT TOTAL AMOUNT AMOUNT THIS ORDER AFTER CHANGE $573,723.61 $583,673.24 $2,742.60 $586,415.84 ORIGINAL CURRENT CONTRACT TIME NEW CONTRACT CONTRACT TIME CONTRACT TIME CHANGE(Add/Del) TIME 75 Working Days 79.5 Working Days 0.5 Working Days 80 Working i• APPROVAL RECOMMENDED APP OVAL 'ECOMMENDED X❑ _ Prof t�c Aluu er Date County E leer Date 61?" OVAI REC MMENDED APP V Engineering S rvices Manager Date Chair,Jefferson County Commissioners Date N N Q U N � { ' I fi4 4 us I I € r 1 iz N •• $ F.N O# Wo0 vj N c n' 7. sr i �_ Q 3; oo o O+ U i O( -I N , ; Him o .- I W • , 1 la z I k W, ;, ( IE'+ I O O� Q�pI # 1H v OMO 1W#2 f f •2#�1• n. # O En �# On € f W ; f < 1 __. .. r---`- f r I v I or d I 1 I i F 1, �, cni b ; k.):' al z alw ..1 0 1 =? of I U 'U' 0 f f 4 i 1 (CD ,I-' 3 0 !{ H;0 # O 0 € O O 0 { coO O f • { f r { I r #� 1 ' o, OO( i 7 C. I I "30Q O O o# #j(;E.f _ i_ �f j 0 IW 3 IX! 1d �1 �,10 #E" 1 ;Wl I 1 I ,_, , aIm I 1 z - cDi i v) # ,H � (A, 1 a 7.iOf 1 2� W t ' i l 3 w zff 22 3a' I a3 b � U 3C01 Ft/ f r, f� CO V j i a Q C Q �' Cr? t f G G F 3 P I { s a) O L" zl N O z a4 U W C)3 ob U W U , NI -- ry f • N I' t fJO O' Q N F ( # Z I I 0 N O # y v 01 #•• 1 lf 2 ' O c+i I)f 18 1Fi G! Z n1 Department of Public Works 0 Consent Agenda Page 1 of 1 Jefferson County Board of Commissioners Agenda Request To: Board of Commissioners Mark McCauley, County Administrator From: Monte Reinders, P.E., Public Works Director/County Engineer Agenda Date: June 27, 2022 Subject: Change Order No. 5, 6, and 7, for SR 116 and Cedar Avenue Pedestrian - Bike Improvements Project, Project No. 1802057, County Road No. 637109, WSDOT Project No. HLP-SR19(006) Statement of Issue: Change Orders No. 5, 6, and 7 with Interwest Construction, Inc. of Burlington, Washington. Analysis/Strategic Goals/Pro's Et Con's: These change orders consists of: Change Order No. 5: Removal of a segment of cement conc. driveway entrance and traffic curb and gutter at the 1ST Street and Cedar Ave. intersection. This work is necessary to correct the Plan dimension of a too-high gutter-lip, correct omission of the detectable warning surfaces by the contractor, and allow for construction of an ADA compliant cement conc. driveway entrance and traffic curb and gutter, for the two proposed pedestrian crossings at that intersection. Change Order No. 6: Removal of unsuitable native material from the Multi-use Path location, and replacement with crushed surfacing top course material to provide for a sound base for the path. Change Order No. 7: Part 1: Addition of crushed surfacing top course to the Vegetated Filter Strip to provide a firmer surface. Part 2: Adjustment of the existing water valve casing to finished grade in the Multi- use Path. Part 3: Adjustment of the vehicle swing gate at the west end of the Multi-use Path to provide clearance above the asphalt pavement. Fiscal Impact/Cost Benefit Analysis: Change Order No. 5 adds $2,742.60 and '/z Working Day. Change Order No. 6 adds $5,141.14 and no Working Days. Change Order #7 adds $3,565.06 and no Working Days. This project is funded at 100% by a WSDOT Safe Route to School Program (State) grant. Department of Public Works O Consent Agenda Page 2 of 2 Recommendation: Public Works recommends that the Board authorize Change Order No. 5, 6, and 7 with Interwest Construction, Inc., and return two originals of each to Public Works for further processing. Department Contact: John Wayand, Project Manager, 385-9377. Revie By: /(z, i/Z— .._ Mark McCaul County Administrator Date