RESOLUTION NO.
16-92
IT IS HEREBY RESOLVED that Chimacum Road, Road Log No.
932507 , from M.P. 0.06 to M.P. 0.44 be improved as follows:
Widen to included two-way left turn channelization, construct
storm drainage facilities, curbs, gutter and sidewalk, surface with
A.C. pavement and install traffic facilities.
IT IS FURTHER RESOLVED that an appropriation from the
officially adopted road fund budget and based on the County
Engineer's estimate is hereby made in the amounts and for the purpose
shown:
PURPOSE
PREVIOUS APPROPRIATION
PRESENT APPROPRIATION
Engineering
$36.000 ($29.927 Fed. Aid)
$43.700 ($36.328 Fed. Aid)
Right of Way
Acquisition $
0
$39.550 ($32.878 Fed. Aid)
$83.250 ($69.206 Fed. Aid)
Sub-Total
$36.000 ($29.927 Fed. Aid)
Construction: $251.200 ($184,160 R.A.P.
XX Contract & $26,573 Fed. Aid)
-- County Forces
$272,200 ($184.160 R.A.P.
& $69,194 Fed. Aid)
TOTAL
$287.200 ($184.160 R.A.P.
& $56,500 Fed. Aid)
$355.450 ($184.160 R.A.P.
& $138,400 Fed. Aid)
XX
This project is included in the officially adopted annual road
program as Item No. 6
The projects hereby made a part of the officially adopted annual
road program in accordance with R.C.W. 36.81.130.
IT IS FURTHER RESOLVED that:
XX
The construction is to be accomplished by contract in accordance
with R.C.W. 36.77.020 et. seq.
The construction is to be accomplished by County forces in
accordance with R.C.W. 36.77.060 and W.A.C. 136.18.