RESOLUTION NO.127-80
COUNTY ROAD PROJECT NO. 491
BEFORE THE BOARD OF JEFFERSON COUNTY CO~rrlISSIONERS OF JEFFERSON COUNTY, WASHINGTON.
In the matter of initiating a county road project designated as C.R.P. 491
It is hereby resolved that ~ Fir street in Paradise Bay Estates ~,
State Road Log /I 46780 , from Mi1epoint 0.00 to Milepoint 0.06
be improved as follows: Widened, graded and drained.
It is further resolved that an appropriation from the officially adopted road fund
budget and based on the county engineer's estimate is hereby made in the amounts
and for the purpoSe shown:
PURPOSE
AMOUNT OF APPROPRIATION
Engineering
Right of Way Acquisition
$250.00
None
Construction:
Sub Total
Contract 0
County Forces <::>
$250.00
$2475.00
$2725.00
Total
OThiS project is included in the officially adopted annual road program
as Item ff
€)The project is hereby made a part of the officially adopted annual road
program in accordance with RCW 36.81.130.
It is further resolved that:
()The construction is to be accomplished by contract in accordance with
R.C.W. 36.77.020 et. seq.
~The construction is to be accomplished by county forces in accordance
~with R.C.W. 36.77/060 and WAC 136-18.
Adopted this ,9 tl day of ~ ,~.