HomeMy WebLinkAboutSDR2022-00028 Site Development Review 901151004, 901142042JEFFERSON COUNTY
DEPARTMENT OF COMMUNITY DEVELOPMENT
621 Sheridan Street | Port Townsend, WA 98368
360-379-4450 | email: dcd@co.jefferson.wa.us
http://www.co.jefferson.wa.us/260/CommunityDevelopment
SITE DEVELOPMENT REVIEW
Per Ordinance No: 09-10033-22 and Jefferson County Code (JCC) 18.40.440, site
development review (SDR) process will provide owners and developers of land an
assessment of site requirements for development of a parcel.
Site development review is a required assessment, prior to development, of the physical aspects and constraints of the site for the purpose of development. While it will not vest a property to development regulations, it provides for a professional analysis of the site
according to current development regulations
Jefferson County Department of Community Development Planning Staff has completed a
site development review on parcel 901151004 and access parcel 901142042. This site development review reflects the conditions of the property at the date the review was completed.
NOTICES:
1. Completion of this Site Development Review does not provide any assurance of future approvals
for onsite sewage disposal or the ability to obtain potable water on the subject property. Use of
any existing septic systems or water supplies for future development are not assured. Any
activities that alter site conditions may limit or prevent future development of an onsite sewage
system or a potable water supply. All future permitting which requires onsite sewage disposal on
the property must comply with JCC 8.15 and WAC 246-272A at the time of application. Future
proposals necessitating determination of adequate potable water must meet County and State
requirements at the time of application.
2. A guaranteed right to development can only be established once a development permit
application or building permit application vests pursuant to JCC 18.40.320.
3. A site development review does not vest a property to any regulations. Additional information may
be required for development permits. Ground conditions may differ from those found in electronic
review. There are no guarantees for development provided from this Site Development Review.
PROPERTY REVIEW: Zoning: The main parcel 901151004 is a zoned Commercial Agriculture 20 (AP-20) and is a conforming parcel at 32.48. The access parcel 901142042 is zoned
Neighborhood/Visitor Crossroad (NC) and is a conforming lot. The lot is 0.21 acres
and used as access only.
Legal Lot of Record Status: Parcel 901151004: This parcel deed history was reviewed, there was no indication of illegal creation of this parcel, Deed history and subsequent legal descriptions is
2
consistent with County approvals. The property has gone through several County reviewed Boundary Line Adjustments (BLAs) with Community Development approval and subsequent recording. The parcel also has several existing permitted legal
buildings on-site. BLA from 5/21/1999 was recorded and approved under Auditor’s
File Number (AFN) 423124. A subsequent BLA was recorded on 6/4/2009 under AFN
543699.
Access Parcel 901142042: This parcel was not reviewed for legal lot status. This parcel is only used as an access parcel and this application for site development review proposes no change to this use. If the applicants or future applicants wish to
ever consider further development, other than access only on this parcel, a legal lot
of record review and determination will be required.
Critical Areas: Shoreline Conservancy for Chimacum Creek, Fish Habitat Stream, Wetlands, FEMA Flood Zone A – High Risk 100-year, Seismic Hazard, and Susceptible (SUSC) Critical Aquifer Recharge Area.
Shoreline Regulations/Wetlands: The parcel contains shoreline jurisdiction for
Chimacum Creek, mapped as Shoreline Conservancy, any new proposed
development within this area, must comply with shoreline permitting requirements.
It is unlikely development will occur in the shoreline, as the shoreline is surrounded by wetlands and wetland buffers. FEMA Flood Zone A: Any development occurring within the flood zone must comply
with FEMA regulations and Jefferson County Code 15.15.
Required Reports: All critical areas are either outside of project area or have been addressed under the zoning approval ZON15-00008 which allows for this phased development. No additional critical area reviews required, unless proposal changes to
extend into critical areas, in which case a revision to the zoning approval would likely
be required with additional special reports.
Stormwater permitting: Stormwater Best Management Practices shall be implemented as conditioned on any permit approvals and as required in the current edition of the Stormwater Management Manual for Western Washington. Jefferson
County has adopted the most current edition of the Stormwater Management Manual
for Western Washington produced by Washington State Department of Ecology.
• Stormwater Clearing Permits are required for ALL property clearing of 7000
square feet or greater. This can be obtained through a building permit or if you wish to clear the property prior to developing you must obtain a separate stormwater permit. This is required prior to clearing for septic installation
• Stormwater Clearing Permits or Vegetation Removal Permits are required for any
tree removal if within a critical area regardless of square feet being cleared.
• Impervious surface includes gravel surfaces.
• Building permits must address stormwater.
o A small project is any impervious surface under 2000 square feet. You must meet minimum requirement #2.
o A medium project is any impervious surface from 2000 to 4999 square
feet or 7000 or more square feet of clearing. You must meet Minimum
requirements #1-#5. Including on site stormwater management.
Jefferson County will request you to design a stormwater management
system as part of your building permit to address roof and other hard
3
surfaces.
o A large project is any impervious surface from 5000 square feet or greater. You must meet all minimum requirements. Jefferson County will
request you to design a stormwater management system as part of your
building permit to address roof and other hard surfaces. If you reach a
large project and your parcel is 5 acres or larger and you are not within an
Urban Growth Area, an engineered stormwater plan is required to ensure low impact design standard is met.
• If you plan on clearing the property and qualify under Department of
Natural Resources (DNR) classification of needing a Forest Practices
Application (FPA) you must work with our department first to obtain a
Class IV General Stormwater Permit with SEPA to avoid a Development
Moratorium. Jefferson County recommends you contact DNR to determine
if your project meets their standard
Next Steps: Apply for Development Permits.