HomeMy WebLinkAboutSDR2022-00003 Site Development Review 701311006JEFFERSON COUNTY
DEPARTMENT OF COMMUNITY DEVELOPMENT
621 Sheridan Street | Port Townsend, WA 98368
360-379-4450 | email: dcd@co.jefferson.wa.us
http://www.co.jefferson.wa.us/260/CommunityDevelopment
SITE DEVELOPMENT REVIEW
Per Ordinance No: 09-10033-22 and Jefferson County Code (JCC) 18.40.440, site development
review (SDR) process will provide owners and developers of land an assessment of site
requirements for development of a parcel.
Site development review is a required assessment, prior to development, of the physical aspects and constraints of the site for the purpose of development. While it will not vest a property to development regulations, it provides for a professional analysis of the site according to current
development regulations.
A guaranteed right to development can only be established once a development permit application
or building permit application vests pursuant to JCC 18.40.320.
Jefferson County Department of Community Development Planning Staff has completed a site
development review on parcel 701311006. This site development review reflects the conditions of
the property at the date the review was completed.
Zoning: This parcel is zoned Rural Residential 1 dwelling unit per 5 acres (RR1:5). This is a conforming lot and is 6.49 acres.
Setbacks: The required setbacks for parcel 701311006 include, 30 feet from E Quilcene Road (the
west parcel setback), a major collector; 5 feet from adjacent residential parcels on the north and
south parcel boundaries; and 100 feet from the rural forest land on the eastern boundary.
Adjacent Zoning and Special Setbacks: The property is adjacent to rural forest land on the eastern parcel boundary. Per JCC 18.20.160, any structures must maintain a setback of 100 feet
from this property boundary. Consideration for reduction of the setback is determined by parcel
constraints and protocols for reduction at the time of application.
Critical Areas: The critical areas present on this property include geologically hazardous areas:
unstable shoreline slope, slight landslide hazard, and a seismic hazard, FEMA Flood zone AE, Critical Aquifer Recharge Area, and Coastal Seawater Intrusion Protection Zone (SIPZ).
Geologically Hazardous Areas: The property contains a seismic hazard, unstable shoreline
slope, and slight landslide hazard area; development within this zone will require a geotechnical
report for the seismic hazard. The applicants have submitted a geotechnical report completed by
Stratum Group on November 21, 2019. The applicants have notarized and recorded a Notice-To-
Title for development in a geologically hazardous area recorded under Auditor’s File Number (AFN) 657389. The geotechnical report is valid until November 21, 2024, for 5 years, per JCC 18.22.905.
FEMA Flood Zone A: The proposal for development is outside of the FEMA Flood ZONE. Any future
development within the FEMA Flood Zone will have to comply with all regulations and flood proof
requirements at the time of submittal.
Shoreline Regulations: Per the shoreline master program, the property contains an area within
2
the Shoreline Conservancy Designation for Quilcene Bay. The proposal that is associated with this SDR is outside of Shoreline Jurisdiction and does not require a shoreline exemption or other shoreline approval. The shoreline buffer is 150 feet landward and shoreline jurisdiction is 200’
landward of the Ordinary High Watermark (OHWM). The shoreline jurisdiction does not cross East
Quilcene Road and therefore is not present where development is proposed.
Required Reports: Geotechnical Report for any development
Stormwater Permitting: The stormwater proposal must comply with the 2019 Stormwater Management Manual for Western Washington.
Legal Lot of Record Summary: This parcel is a legal lot of recorded because it was subdivided by
survey in 1987 by Pope Resources. This was allowed per subdivision exemptions under Revised
Code of Washington (RCW) 58.17.040(2) and Jefferson County Ordinance No. 1-79, Section 3.40 (9) Exemptions: Divisions of land into lots or tracts where the overall density of the entire parcel being divided does not exceed on unit per five (5) acres, with specific requirements being met for
this division.
Next Steps: Apply for development permits including, but not limited to septic and building
permits.