From:
Sent:
To:
Cc:
Subject:
Zoe Ann Lamp
Tuesday, February 28, 2006 12:04 PM
'James parker'
Stacie Hoskins
RE: Beckett Point - Conversion
Jim,
Quilcene Permit - The permit is on Al's desk to review. We're still
expecting to have it ready for you tomorrow. As soon as we're finished
with it I'll e-mail you.
Beckett Point - No date for a hearing yet. When you pick up the Quilcene
permit tomorrow I'll have a packet of comments for you to address. After
you respond to the comments I will do my staff report and schedule the
hearing. As far as bald eagles are concerned. . I spoke with Shelly
Ament last week and she said there is no eagle plan required. Since there
are eagles in the area she would like you to keep as many trees as
possible, however, she's not requiring an eagle plan.
Do you have other information regarding the bald eagles? please advise.
Sincerely,
Zoe Ann Lamp
Associate Planner
Jefferson County
Department of Community Development
621 Sheridan Street
Port Townsend, WA 98368
phone: 360-385-9406
Fax: 360-379-4473
-----Original Message-----
From: James parker [mailto:jparker@jeffpud.org]
Sent: Tuesday, February 28, 2006 11:57 AM
To: Zoe Ann Lamp
Subject: RE: Beckett Point - Conversion
Zoe I have a board meeting tomorrow night. Do you know when the
shoreline hearing is for the Beckett Point system. Engineers are
worried if it is too late we can not do anything this year because of
the bald eagles.
Also can I pick up the Quilcene permit tomorrow.
Thanks
1
JIm
-----Original Message-----
From: Zoe Ann Lamp [mailto:zlamp@co.jefferson.wa.us]
Sent: Thursday, January 12, 2006 2:50 PM
To: James parker
Subject: RE: Beckett Point - Conversion
Jim,
We discussed the project today in the staff meeting. John Nisbet
(Nisbet Timber phone: 732-7700) has been talking to Greg Ballard
(planner in our office) about the Forest Practices Application. The
information from parametrix covers everything I need. John doesn't have
to submit anything else. No additional fees are needed at this time
because the PUD already paid for SEPA and the review can be covered
under the main project.
Looks like we're on schedule for the Notice of Application to be printed
in the January 18th edition of the Leader.
You'll want to come in and get the signs before Wednesday. Our office
is closed for MLK Day on Monday, Jan. 16th.
Cara will have the notice ready to pick up on Tuesday afternoon.
Please let me know if you have any questions.
Sincerely,
Zoe Ann Lamp
Associate Planner
Jefferson County
Department of Community Development
621 Sheridan Street
Port Townsend, WA 98368
phone: 360-385-9406
Fax: 360-379-4473
-----Original Message-----
From: James parker [mailto:jparker@jeffpud.org]
Sent: Monday, January 09, 2006 10:16 AM
To: Zoe Ann Lamp
Subject: RE: Beckett Point - Conversion
Thanks I forwarded your message to parametrix, so you may here from them
Jim
-----Original Message-----
From: Zoe Ann Lamp [mailto:z1amp@co.jefferson.wa.us]
Sent: Monday, January 09, 2006 10:02 AM
2
L
To: James parker
Subject: RE: Beckett Point - Conversion
Jim,
Looks like the conversion was discussed in the pre-application
conference. It was discussed that the forest conversion was going to be
completed prior to the submission of a permit for the improvements. I
just mentioned this project to another planner in the office. He said
that John Nesbitt is working on it but he hasn't turned it in yet.
Stacie Hoskins, Greg Ballard, Al Scalf and I will be getting together
this week to discuss the project.
Sorry, I had hoped to get it noticed this week but with this coming up I
won't be able to. I will let you know the results of the meeting.
Sincerely,
Zoe Ann Lamp
Associate Planner
Jefferson County
Department of Community Development
621 Sheridan Street
Port Townsend, WA 98368
Phone: 360-385-9406
Fax: 360-379-4473
-----Original Message-----
From: James parker [mailto:jparker@jeffpud.org]
Sent: Monday, January 09, 2006 9:00 AM
To: Zoe Ann Lamp
Subject: RE: Beckett Point - Conversion
Zoe:
I was not aware of the requirement, what is necessary to make the
conversion?
Jim
-----Original Message-----
From: Zoe Ann Lamp [mailto:zlamp@co.jefferson.wa.us]
Sent: Monday, January 09, 2006 8:28 AM
To: James parker
Cc: Ross Goodwin (E-mail)
Subject: Beckett Point - Conversion
I was reviewing Beckett Point Sanitary Sewer System Improvements case
with Stacie Hoskins. As we were going through everything we realized
Beckett Point has not addressed the conversion of the 5 acres drainfield
area from forested land to non-forestry use. What has hapP€!l)..~49P this?
3
" ...h,l,",_ __~., u..
",.3.. _<'"~.,,<.
..
Please advise.
Sincerely,
Zoe Ann Lamp
Associate Planner
Jefferson County
Department of Community Development
621 Sheridan Street
Port Townsend, WA 98368
phone: 360-385-9406
Fax: 360-379-4473
-----Original Message-----
From: James parker [mailto:jparker@jeffpud.org]
Sent: Friday, January 06, 2006 3:33 PM
To: Zoe Ann Lamp
Subject: RE: Comments on Quilcene Water System and Beckett Point
Probably just as well to pay for 6 more.
will be by. Thanks for your help.
Just let me know when and I
Jim
-----Original Message-----
From: Zoe Ann Lamp [mailto:zlamp@co.jefferson.wa.us]
Sent: Friday, January 06, 2006 3:30 PM
To: James parker
Subject: RE: Comments on Quilcene Water System and Beckett Point
Jim,
I have been working on Beckett Point most of the day trying to complete
the information necessary to notice it. I have not had a chance to
review the Quilcene Water Project. Looks like it will be Monday before
I'll be able to look at it.
After looking at the Beckett Point project I'd like it noticed in 7
locations. Because this is a shoreline application it will need to be
up for 30 days. Do you have enough signs left over from other projects
or do you need to pick up more? You paid for one with the application.
Each additional one will be $8.00. When you pick up the signs we can
discuss the posting locations.