Loading...
HomeMy WebLinkAboutLog013 " .- r ( " Potential Timeline for Port Ludlow Marina Expansion Based on pile driving beginning September 2, 2003 October 29,2002 Following is a draft outline of a schedule developed to allow construction of the marina expansion to begin September 2, 2003. Key items/dates in the schedule are: · Issuance of the Final SEIS for the Resort (this allows processing of the Jefferson Co. Shoreline Permit); · Issuance of the Jefferson Co. Shoreline Permit (this allows submission/approval of the Jefferson Co. Building Permit); · Signed contract with the construction contractor (do you want to do this before you have an approved County Shoreline Permit?); · Ordering piling (a significant cost and a long lead time; PLA may need to authorize purchase of piling before the Building Permit is issued). The following schedule is tight, and assumes the Resort SEIS will proceed in a straightforward manner, so we do need to start ASAP. I have a call into Josh reo how long it will take after the Resort FSEIS is issued to get the Shoreline Permit. schedule also assumes the COE Section 10 Permit and the WDFW HP A will prior to the County Shoreline Permit. RMI and others prepare pre- draft DSEIS 21 days (assumes no new alternatives will be developed or new substantive issues will be introduced Three months (assumes technical studies will be complete within 6 - 8 weeks, then incorporated into the DSEIS 21 da s 1 da 30 da s Three weeks (assumes no major new alternative and no collection of new data Two weeks 1 da ???? Ma 26 -June 9 June 13 Late June? Dec. 2 - Dec. 23 Dec. 2 - March 3 Count Review Issue DSEIS Circulate DSEIS Prepare FSEIS March 3 - March 24 March 31 March 31- A ril30 May 5 -May26 Count Review Issue FSEIS Shoreline Development Permit Desi n Process Prepare Performance Packa e for Pro' ect Solicit Contractor Pro osals- Five weeks January 7 - Feb. 11 One week Feb. 11 - Feb. 18 LOG ITEM # "3 Page \ of~ ----., . .. r ( '" (-<" 3 contractors Contractors prepare ro osals Evaluate Contractor' Pro osals, Select Contractor Contractor Contract Negotiations, Signed Contract, Insurance Forms, Bonds, Notice to Proceed Design process (need to sign contract with contractor/have finalla out of marina Obtain Buildin Permit Order and Deliver Piles Begin Pile Driving (assumes floats installed after piling) Three weeks Two weeks Three weeks Eight weeks Two weeks Ten weeks Two months RMI 24 wf\99\O 14\pladesign\timelineforportludlowmarinapiledriving.doc Feb. 18 - March 11 March 11 - March 25 March 25 - April 15 April 15 - June 10 June 10 - June 24 June 24 - S t. 2 September 2 - Oct 31 (allowable window based on operations and ermittin