Loading...
HomeMy WebLinkAboutInterwest Construction, Change Order No. 5 - 120522JEFFERSON COUNTY Sheet 1 of 1 DEPARTMENT OF PUBLIC WORKS Change 5 Date: 11/21/2022 CHANGE ORDER Order No. Ordered by County Engineer under terms of Section 1 - 04.4 of the Standard Specifications Contract Na. Change proposed by Contractor To: Interwest Construction, Inc 609 North Hill Blvd Endorsed by: Interwest Construction Inc Burlington, WA 98322 ntrector Firm Name Project Title JUMPI Project at HJ rg tureDdle 77t1e Consent given by Surety: (when required) Carrol Park sy: Afforney-in-fact Date You are ordered to perform the following described work upon receipt of an approved copy of this change order. The Contract specifications are hereby modified as follows: New item 65 - Bollard Installation & Hioh Visibility Fence Re -installation This change order provides for the purchase, installation and painting of three bollards, and re -installation of high visibility safety fencing around the hydroseeded area Inside of the playground, Estimated cost = $4,680.52 i All work materials and measurement to be In accordance with the provisions of the standard specifications and special provisions for the type of construction Involved. ORIGINAL CURRENT ESTIMATED ESTIMATED CONTRACT CONTRACT NET CHANGE CONTRACT TOTAL rr AMOUNT AMOUNT THIS ORDER AFTER CHANGE ;= 1 r $756,385.60 $770,836.41 $4,680.52 $775,516.93 ORIGINAL CONTRACT CURRENT CONTRACT CONTRACT TIME NEW CONTRACT TIME days TIME (days) CHANGE (Add/Del) TIME (days) X _ ' .., AP ROV L R OMMENDED APPROVA RECOMMEN�P Project Me agar Date County ginner Date A ROV L R OMMENDED AP ED 4 i S: `"" t u yu 121 S122 EngineeriA6 Se 'ces Manager Date Ch tr, Jefferson County Commissioners Date Jefferson County Universal Movement Playground (JUMP!) Project Force Account Calculations Change Order No 5: $ 4,680.52 Installation and painting of three bollards, and re -installation of high visibility safety fencing around the hydroseeded area inside of the piaygrouna. Date 10/26, 10/27, 1O/28, 10/31, 11/1 Regular Time Equipment Hours Hourly Operating Cost Amount 08-1241-Ton Chevrolet Truck 18 $ 22.69 $ 408.42 21% Markup $ 85.77 Labor $ 494.19 Regular Time Worker Hours Wage+Benefits from L&I Amount Laborer Foreman (Tim Colville) 18 $ 70.52 $ 1,269.36 Laborer (Mattew Malcom) 4 $ 59.86 $ 239.44 31% Markup $ 467.73 $ 1,976.53 Material Qty. Bollard Paint 1 $ 80.38 $ 80.38 Bollard Concrete 10 $ 4.09 $ 40.90 Removable Bollard 1 $ 725.00 $ 725.00 Static Bollard 2 $ 490.00 $ 980.00 21% Markup $ 383.52 $ 2,209.80 Total $ 4,680.52 To: From: Agenda Date: Subject: Department of Public Works O Consent Agenda Page 1 of 1 Jefferson County Board of Commissioners Agenda Request Board of Commissioners Mark McCauley, County Administrator Monte Reinders, Public Works Director B�, December 5, 2022 Change Order No. 5, JUMP! Project at HJ Carroll County Park, Chimacum, WA. Statement of Issue: Authorization of Change Order No. 5 to the contract with Interwest Construction Inc. (ICI) for the construction of the JUMP! Project; a new all-inclusive playground at HJ Carroll County Park. Analysis/Strategic Goals/Pro's at Con's: Change Order No. 5 provides for the purchase and installation of (3) bollards and the re -installation of high visibility fencing to protect hydroseeded playground area until grass is established. Fiscal Impact/Cost Benefit Analysis: This change orders will increase the contract amount by $4,680.52, from $770,836.41 to $775,516.93. Construction is funded through a combination of a $500,000 RCO Grant, a Jefferson County Capital Improvement Fund contribution of $550,000, and other grants, pledges and cash donations. Recommendation: Public Works recommends that the Board execute three Change Order No. 5 documents with ICI and return two (2) to Public Works for further processing. Department Contact: Eric Kuzma, Engineering Services Manager, 385-9167. Reviewed By: Mark McCain , County Administr Date