HomeMy WebLinkAboutTetra Tech Hadlock Sewer Department of Public Works
O Consent Agenda
Page 1 of 1
Jefferson County
Board of Commissioners
Agenda Request
To: Board of Commissioners
Mark McCauley, County Administrator
From: Monte Reinders, Public Works Director/County Engineer
Agenda Date: February 13, 2023 loo
Subject: Supplement #5 - Contract with Tetra Tech, Inc.
Final Design - Port Hadlock Sewer
Statement of Issue: This contract with the County's sewer design team led by Tetra Tech,
Inc. is for final design and specifications for the wastewater treatment facility and
pressurized sewer collection system for the Core Area (Phase 1). Supplement #5 adds scope
and budget to complete the final plans and specifications for the Phase I Site Work contract
which is scheduled to go to bid at the end of February.
Analysis/Strategic Goals/Pro's Et Con's: This Supplement will complete the Plans and
Specifications needed to go to bid advertisement in late February on the Phase I Site Work
contract for the Port Hadlock Sewer. The Phase I Site Work contract will include the
earthwork for the wastewater percolation pond, utilities to the treatment plant site, access
road to the site, parallel influent sewer lines leading to the site from SR-116, and main
effluent sewer pipe leading to the percolation pond. Tetra Tech is addressing changes
requested by the County and PUD to finalize the bid package. Many of the changes result in
cost savings that will more than offset these design costs.
Fiscal Impact/Cost Benefit Analysis: The additional budget is $72,293 as detailed in Exhibit B
to the Supplement. An additional $20,000 is included as a design contingency to cover
unanticipated work bringing the total Supplement to $92,293. These costs are covered by
County ARPA funds dedicated to this project.
Recommendation: Please sign three (3) originals of Supplement #5 and return two (2) fully
executed originals to Public Works.
Department Contact: Monte Reinders x242
Reviewed By:
Mark McCauleyjVounty Administrator Da
Tetra Tech Supplemental Agreement # 5
FOR REFERENCE ONLY
Below are direct links to the previous supplemental agreements and the original agreement.
To view these, either use the links below or navigate to the agreements from the Laserfiche
Weblink Portal page https://test.co.jefferson.wa.us/WeblinkExternal. From this page open the
Board of Commissioners folder, then open the Contracts folder. From there open the folder for
the corresponding year and scroll to the Tetra Tech agreements within that year to locate the
documents below.
Original Agreement—4/21/2020
https://test.co.'efferson.wa.us/WeblinkExternal/DocView.aspx?id=2384154
Supplemental Agreement#1-11/2/2020
https://test.co.'efferson.wa.us/WeblinkExternal/DocView.aspx?id=2601659
Supplemental Agreement#2—11/22/2021
https://test.co.'efferson.wa.us/WeblinkExternal/DocView.aspx?id=3338923
Supplemental Agreement#3—2/14/2022
https://test.co.*efferson.wa.us/WeblinkExternal/DocView.aspx?id=3399021
Supplemental Agreement#3—11/7/2022
https://test.co.4efferson.wa.us/WeblinkExternal/DocView.aspx?id=4120942
%osear corm
CONTRACT REVIEW FORM
(INSTRUCTIONS ARE ON THE NEXT PAGE)
CONTRACT WITH: Tetra Tech-Supplement#5 Contract NA cW 2,3 •-O/?j
Contract For: Port Hadlock-Sewer Final Design Term: 6/30/2023
COUNTY DEPARTMENT: Public Works
Contact Person: Monte Relnders
Contact Phone: 360.385.9242
Contact email: mreinders@co.jenersonwaus
AMOUNT: $92,293 PROCESS: Exempt from Bid Process
Revenue: $92,293(ARPA) Cooperative Purchase
Expenditure: $92.293 Competitive Sealed Bid
Matching Funds Required: $o Small Works Roster
Sources(s)of Matching Funds Hadlcck Sewer Fund Vendor List Bid
RFP or RFQ
X Other:Supplement
APPROVAL STEPS:
STEP 1: DEPARTMENT CERTIFIES COMPLIANCE WITH JCC 3.55.080 AND CHAPTER 42.23 RCW.
Monte Reinders� ' —
CERTIFIED: ✓ N/A
Signature. Date
STEP 2: DEPARTMENT CERTIFIES THE PERSON PROPOSED FOR CONTRACTING WITH THE
COUNTY (CONTRACTOR) HAS NOT BEEN DEBARRED BY ANY FEDERAL, STATE, OR LOCAL
AGENCY. ognxy.a w"r r°+,Nerro,r.
ON'.L.Ua.E.mrwnd,rye.o Nr,n°n w u.,
Monte Reinders l, d
Fm.D'I—MGN gIhIgei 1
CERTIFIED• ✓ N/A• "°"" '°"°"°'"",.�R.
or.:ama as oai u:.o n ura
Signature Date
STEP 3: RISK MANAGEMENT REVIEW(will be added electronically through Laserfiche):
Electronically approved by Risk Management on 2/3/2023.
STEP 4: PROSECUTING ATTORNEY REVIEW(will be added electronically through Laserfiche):
Electronically approved as to form by PAO on 2/5/2023.
Pre-approved contract form.
STEP 5: DEPARTMENT MAKES REVISIONS & RESUBMITS TO RISK MANAGEMENT AND
PROSECUTING ATTORNEY(IF REQUIRED).
STEP 6: CONTRACTOR SIGNS
STEP 7: SUBMIT TO BOCC FOR APPROVAL
1
Supplemental Agreement Number: #5 Organization,Address, and Phone:
Tetra Tech, Inc.
1420 Fifth Avenue, Suite 600
Agreement Number: N/A Seattle,WA 98101
Project Number: 405 1693-5 Execution Date: Completion Date:
4/20/2020 6/30/2023
Project Title: Port Hadlock Wastewater Maximum Amount Payable:
System—Final Design $1,667,413
Description of Work: Final design of the Port Hadlock Wastewater Treatment Plant and
Collection System for the Port Hadlock"Core Area".
SUPPLEMENTAL AGREEMENT
Jefferson County hereby amends the agreement with Tetra Tech, Inc. ("the Agreement"), originally
executed on April 20, 2020.
All provisions in the Agreement remain in effect, except as expressly modified by this
Supplemental Agreement.
The changes to the Agreement are described as follows:
I.
Scope of Services is hereby changed to read:
Add Scope of Work(SOW) as described in Exhibit A-1 for completion of the Phase I Sitework
Plans and Specifications.
II.
Time for Performance is hereby changed to read:
No Change. The Agreement shall terminate on June 30, 2023 unless amended in writing prior to
this date.
III.
Payment is hereby changed to read:
Add$72,293 for work described in the attached SOW. Add$20,000 design reserve for
unanticipated needs, only to be used with express written permission of the County. See Exhibit B.
Supplemental Agreement(to A &B) Contract C, Version 1, Risk Legal Review Date 04/30/2018 Page I of 2
This Supplemental Agreement shall be effective upon execution by both parties. Work performed
consistent with the Agreement prior to execution of this Supplemental Agreement is hereby ratified.
In witness whereof, the parties hereto have executed this Supplemental Agreement as shown below.
COUNTY OF JEFFERSON
(Consultant Firm Name) BOARD OF COMMISSIONERS
Tetra Tech Inc.
Consultant's Name Kate Dean, District 1 Date
Consultant's Si ature Heidi Eisenhour, District 2 Date
February 3, 2023
Date Greg Brotherton, District 3 Date
Approved as to form only:
PRE-APPROVED CONTRACT FORM
Philip C. Hunsucker Date
Chief Ci eputy secuting Attorney
!ok-1
Monte Reinders,P.E. Date
Public Works Director/County Engineer
Supplemental Agreement(to A&B) Contract C, Version 1, Risk Legal Review Date 04/30/2018 Page 2 of 2
EXHIBIT A-1
SCOPE OF WORK
JEFFERSON COUNTY DEPARTMENT OF PUBLIC WORKS
PORT HADLOCK WASTEWATER SYSTEM DESIGN UPDATE
SERVICES
SUPPLEMENT NO 5
ADDITIONAL TREATMENT PLANT DESIGN SERVICES
PHASE 1 TREATMENT PLANT SITE/CIVIL BID PACKAGE
GENERAL - ADDITIONAL DESIGN SERVICES
The scope of services in this supplement provides additional services to incorporate design changes and
additional design services associated with the Phase 1 Treatment Plant Site/Civil Bid Package for the
wastewater treatment plant design. These services are to incorporate the changes described in the
tasks below and complete the designs for the Phase 1 Treatment Plant Civil Bid Package. treatment
plant and collection system for bidding.
TASK 100 - PROJECT MANAGEMENT (ADDITIONAL DESIGN)
This task includes supplemental budget to track, monitor, plan, and manage the work within the scope
of this supplement.
Work in this task is described as follows:
• Progress Updates- Progress updates will be held by telephone approximately every other week
with the County to coordinate work activities and keep the County informed of progress to date.
It is assumed the work within this supplement will be accomplished within 3 months of notice to
proceed and there will be up to 2 progress updates during that period between the County and
the Consultant Project Manager.
• Progress Reports and Billings-Tt will include brief monthly progress reports along with monthly
invoices. Progress reports will contain information on major activities, anticipated actions, and
outstanding issues to be resolved.
Work Products:
• Summary of Action Items and follow up.
• Monthly progress reports and invoices
TASK 200 — RECLAMATION PLANT & INFLUENT PIPELINE DESIGN
UPDATE
Subtask 200.5 — 100% Plans, Specs, and Estimate (Phase 1 Treatment
Plant Site/Civil Package)
Incorporate County plan markups, review WSDOT specification package and incorporate technical
special provisions. Submit bid ready plans and specifications.
Work activities to be completed in this task are as follows:
• Incorporate markups to the plans received by the County on January 11, 2023, including the
following:
• Swap out sheet pile wall with welded wire wall.
• Change single 10-inch influent sewer to two parallel 6-inch influent sewers.
• Miscellaneous changes related to the work split between Phase 1 and 2.
• Revise access road grading to drain to the east.
• Re-size drainage swale (as necessary)
• Add water line on percolation pond property
• Incorporate water service revisions
• Incorporate electrical &fiber optic service revisions a add conduit sections.
• Review County's draft specification package in WSDOT format
• Review technical specifications and prepare special provisions for technical items such as pipe
and materials
• Provide pre-final check set to the County and incorporate any minor pickups
Work Products:
• Pre-final check set(plans and specifications)
• Final Treatment Plant Plans and Specification package
TASK 5000 — UNANTICIPATED DESIGN RESERVE
This task provides a $20,000 reserve budget to be used at the County's discretion. This budget is
reserved will not be used without written authorization of scope and authorized budget to be used
against this reserve.
EXHIBIT B
Rev,sicn Date Labor Plan
Price Proposal Feb 01,2023 1b ResourCt
Port Hadlock
1JS-11Se1-ltkkJ ••
Submitted to:1e erson County Attn:Monte Rein ers
t E e} g
CunGact Type.Gust Plua f a 2
TOtal
Schedule labor J.
Hrs - -
ProjedPhaes/Tasks cram lhru Ncmns 413 I I; L yl t .I 30 lti 16 • 16 92
PART A-RECLAMATION PLANT A IWWENT 21PELINE
lOD Project Manae�t IAMO Disisn/9W) 17 12 1
100.4 Addobnal V'OUecs M-etingc(21 01.01,121 WIV21 1:] ;n 234 R 6 1
/M ROrma�Q rand
2W Reclaeatlon Plant i Infuent Pipeline DesI ce 396 3 1 16 92 30 30 la is 1 4 36 sa
100.5 10?N►td,.,51 w&6Un.al.tS�..yd.ta.wralrw6t0 U-1 3!a a 10 92 w 30 to la 2 + 1e is
P.— - ••:Hfcn l±-,er 01MI121 12/31/23)COW? awlacd wa.w,n n, OIAII21 1229V23 �
200.i06 Dual i Inch t,Ilmot,,U 01101/23 12/33/23
20o 509 K&ar Chang"to Phr* she PAtx l Wock Selo r�ti21 12/3 V?3 I
cr; r,. :Lt . r;,d 1:.�•.I.:. D 1121 1 23
01N1/21 12BV23 -
oLMI/a 12/sv23
m/n,ha ,�nVsa
soon-unanupand oasten tvwrw uyul/is a/svts u.7 :• z3+
Totalsi OV01/13 I 12/3V13 I 1t.7 I 1 1 4131 15 I 11 26 1 92 1 1 30 1 301 1. 1e 1 I 1 •1 18 1 92
EXHIBIT B
Price Proposal Fe 01, 2023
Feb O1, 2023
Port Hadlock
135-12562-20003
Submitted to:1e arson County Attn:Monte Rein ers Unit Rate s
Itenns> ntvrr,ce�
� u„e Raeq, YJ 55
Contract Type_Cost Plus _ $
Unit> rtnli:
Schedule ° o - < Cvrged to- 11AE
Project Phases/Tasks :m 200
PART A•RECLAMATION PLANT&INFLUENT PIPELINE
200 Project Management)Adldrt'I Design/8&101) a 200
100.4AdAItiIProgpressMeetings{21 011010) 12J3112A 1- : 2n 214 I;I
100.5Proress Reports and Billmgs 01;01121 12,r31/23 1:7 26 234 3
200 Reclamation Plant a Influent Pipelline 0"gn UpIdete 4 16 92 76 2
200.S 100%Plans,Specs&Estimate(Complete outstanding ixms) 4 15 1 22 76 2
,I r 01101J23 12131,r23
011111171 12Ji 3/21 I .
I-
i;
I, L:.. I .•. 011ou21 12131n3 � .
01101J23 12F31/23
r, 0110112i 12111i2; �
01M103 12111113 I I a
S000-Unaticipated Design Row" o1•w1/23 12/31/23 11.7 26 234
Totals o1.1oin3 12J im I 11.2 , ib 1 92 1 76 4 2 Qm. ,W s=• 200
EXHIBIT B
Price Proposal Fevis-ion Date: Price Summary/Totals
Feb 01, 2023 Task Pricing Totals 84,06:
Port Hadlock 12.90%CP fee(appl ed to labor) S,233
TeTfldogy use Fe2
1 33-1 25 62-2 0003 Total Price 9z,z93
Su mitres tn• v cr-,nn rrrinty Attn- Vtnntc+ P.n,r ure
Pr cing by Resource
COltra:_t Ivpe:Co%l Plus
Task Pricin
�nl:n
Schedule RAG Esc Libor Subs Tra,el Mat'.&1:�uip 0DCs Tata s
Project I'ho-,c,/Taslr, n., .,..,,•, o anc billy A.uuu 1_Z IILt 04,Ub1
PART A RECLAWTICN P1ANT&INFLUENT PIPELINE
100 Project ManWrmnt lUMO Daign,%&F) 1fM 112 110 3.991
100 4 Ad&ionalProgress Meetl,gs(.I 31101l23 12/i1123 I: i n .a 1,VA tin I
100.LProm"Repwh and liltingr 71103f27 12AV32 I.7 X. _2.i 1,171
200 Reclamation plant&Irfluent Pipeline Deal n U ate 60,090 io.CWD
100.9 100,Plar,,ip—t Latinal.(:.-plate 60,)GO 60.0w
3VOW) 12/3123
milo 73 I7fi1I23
31xvii 1�/11a1
MAY23 12,iA123
:)Imi 23 12.1In3
)IMM 1241/23
31101/13 12/IW3
S000 Unaticipated DrsignResrrve )1AVn 12I.1J23 31.7 25 J234 Z),000 20,1)Lb
Totals )VOV23 1 12/511=1 11.1 O W% 6311119 2C,000 132 110 84,061