Mark McCauley, County Administrator
From: Monte Reinders, P.E., Public Works Director/County Engine
Agenda Date: May is,, 2023
Subject: Center Road 211 Overlay MP 10.34 to MP 14.58 Project
Project No. 18020960, CRAB Project No. 1622-01
RAP Project Agreement Amendement No. 1
Statement of Issue: The Board is asked to execute the attached County Road
Administration Board (CRAB), Rural Arterial Program Project Agreement for
Construction Proposal, Amendment No. 1, for the Center Road 211 Overlay MP 10.34 to
MP 14.58 Project.
Analysis/Strategic Goals/Pro's Ft Con's: Jefferson County typically schedules
repaving of major county roads at a 20-25 year interval. The two road segments
included in this Center Road project were repaved in 1999 (25 years) and 1994 (30
years). Repaving of these segments of Center Road now will restore the road surface
before the road deteriorates to a point that reduces safety and to where significantly
more extensive repairs would be required.
Fiscal Impact/Cost Benefit Analysis: CRAB authorized $277,400.00 in Rural Arterial
Trust Account (RATA) funds on June 14, 2022 for the 2021-2023 Biennium. With this
amendment CRAB is authorizing an additional $1,200,000.00 in the 2023-2025
Biennium. Execution of this Amendment No. 1 will allow use of the additional RATA
funds for this project.
Recommendation: The Board is requested to execute all three (3) original
Amendment No. 1 documents, and return all three to Public Works. Following
execution of the amendment by CRAB, one fully executed original amendment will be
returned to the BOCC.
Department Contact: John Wayand, Project Manager, 385-9377.
Dat
STATE OF WASHINGTON - COUNTY ROAD ADMINISTRATION BOAR❑
RURAL ARTERIAL PROGRAM
PROJECT AGREEMENT FOR CONSTRUCTION PROPOSAL
AMENDMENT NO. 1
Submitting County: Jefferson Project Number: 1622-01 Date Approved: 04/21/2022
Road Number(s) Road Name(s) BMP(s) EMP(s) Segment #
93150 Center Road 10.340 14.580 1
This is Amendment No. 1 to the above described Project Agreement, between the County of Jefferson, hereinafter the "County"
and the State of Washington County Road Administration Board, hereinafter the "CRABoard."
WHEREAS, the COUNTY and CRABoard desire to amend the original Project Agreement to allow an increase in authorized RATA
funding under the conditions described in WAC 136-161-070.
NOW, THEREFORE, pursuant to chapter 36.79 RCW and in consideration of the terms, conditions, covenants, and performance
contained herein, or attached and incorporated and made a part hereof,
IT IS MUTUALLY AGREED AS FOLLOWS:
The following new language is added as section 15 to the Project Agreement:
Authorized RATA Funding is increased to $1.477,400 per CRABoard approval dated April 13, 2023.
2. All Other terms and conditions of the original Project Agreement shall remain in full force and effect except as modified by
this Amendment No. 1.
IN WITNESS WHEREOF, the PARTIES hereto have executed this AMENDMENT No. 1 as of the PARTY's date last signed below.
COUNTY ROAD ADMINISTRATION BOARD: Jefferson COUNTY:
By: By
Date:
Date:
App vrd as to arm onlyr
G . e. I � I'h"e.F,/.. �3
Philip C. Huns'u *er, Chief ['rrtl mpu,., l'roAr 1,iey
Jefferson County Prosecuting Attorney's Office
Page 1 of 1 AMENDMENT NO: 1
STATE OF WASHINGTON - COUNTY ROAD ADMINISTRATION BOARD
RURAL ARTERIAL PROGRAM
PROJECT AGREEMLNT FOR c t RUCTION PROPOSAL
Submitting County:
Jefferson Project Number: 1622-01
--Date Approved: 04/21/2022 AUTHORIZED RATA FUNDS: $277,400
Road Road Name(s) BMP(s) EMP(s) Segment #
93150 Center Road 10.340 14.580 1
The State of Washington County Road kdministration Board (CRABoard) and Jefferson County (County) mutually
agree as follows:
(1) The funds hereby authorized are for completion of the proposed project as defined by chapter 36.79 RCW
Roads and bridges — rural arterial program.
(2) The County is in compliance with the provisions of chapter 136-150 WAC regarding eligibility for Rural
Arterial Trust Account (RATA) funds. If the County is found not to be in compliance with these provisions, such non
compliance may be cause for the CRABoard to withdraw or deny the Certificate of Good Practice of the County and
require pay back of any RATA funds that have been paid to the County for this project.
(3) If the project is reconstruction, the County shall gain approval from WSDOT (chapter 43.32 RCW) for all
deviations from the design standards listed in the Local Agency Guidelines prior to construction.
(4) If the project is 3R (resurfacing restoration and rehabilitation), the County shall document its design
considerations for the proposed improvements in keeping with 311 standards as listed in the Local Agency Guidelines.
(5) The project shall be constructed in accordance with the information furnished to the CRABoard, and the plans
and specifications prepared by the county engineer.
(6) Phased construction methodology is permitted upon notification by the county engineer of the phasing plan as
authorized under WAC 136-170-030. Failure by the county to notify the CRABoard of phasing plan at least 15 days
prior to commencement of construction may result in withdrawal of funding by the CRABoard and county forfeiture of
all RATA funds expended.
(7) The County shall notify the CRABoard when a contract has been awarded and/or when construction has
started, and when the project has been completed.
(8) The County shall reimburse the RATA in the event a project post audit reveals improper expenditure of RATA
funds.
(9) Costs of the project which exceed the amount of RATA funds authorized by the CRABoard, set forth above,
and the required matching funds and other funds represented by the county to be committed to the pi o�ieet, shall be paid
by the County as necessary to complete the project as submitted to the CRABoard.
RAP Project Number: 1622-01 --,Page 1 of 2
(10) Matching funds and other funds represented to be committed to the project shall be available as necessary to
implement the projected development of the project as set forth in the construction proposal prospectus.
(11) The CRABoard hereby agrees to reimburse the county from RATA funds allocated, and not otherwise, for its
reimbursable costs not to exceed the amount above specified.
(12) The CRABoard will reimburse costs incurred by the County based on project progress as certified by the
county engineer within the CRABoard's RAP Online project management application by monthly progress payment
vouchers received and approved on individual projects in the order in which they are received in the CRABoard office,
subject to the availability of RATA funds apportioned to the region. Such obligation to reimburse RATA funds extends
only to project costs incurred after the date of project approval by the CRABoard.
(13) Either the CRABoard or the County may request changes to the provisions contained in this agreement. Such
changes shall be mutually agreed upon and incorporated by written amendment to this agreement. No variation or
alteration of the terms of this agreement shall be valid unless made in writing and signed by authorized representatives
of the. CRABoard or the County hereto.
(14) During the term of this agreement and for a period not less than six (6) years from the date of final payment by
the CRABoard, the records and accounts pertaining to this agreement are to be kept available for inspection and audit
and copies of all records, accounts, documents, or other data pertaining to the agreement will be furnished upon
request. If any litigation, claim, or audit is commenced, the records and accounts along with supporting documentation
shall be retained until said litigation, claim, or audit finding has been resolved even though such litigation, claim, or
audit continues past the six year retention period.
IN CONSIDERATION of the allocation by the CRABoard RATA funds to the project in the amount set out above, the
County hereby agrees that as condition precedent to payment of any RATA funds allocated at any time to the above
referenced project, it accepts and will comply with the terms of this agreement, including the terms and conditions set
forth in Chapter 49, Laws of 1983, 1st Ex. Sess. (chapter 36.79 RCW); the applicable rules of Title 136 WAC and all
representations made to the CRABoard upon which the fund allocation was based; all of which are familiar to and
within the knowledge of the county and are incorporated herein and made a part of this agreement, although not
attached.
This agreement supersedes all prior agreements issued using the project number listed above and shall be valid and
binding only if it is signed and returned to the CRABoard office within 45 days of its mailing by the CRABoard.
COUNTY ROAD ADMINISTRATION BOARD:
t �
By- ;
Date' t
JEFFE ON COUNTY:
By:
C%rr C�oCC
Date: 4P14e 17, Z--
Anomved as to r I
01, • Date- 2 1-
Philip C. Hunsucker, dhief Civil Deputy Pros ing ttomey
Jefferson Countyprosecuting Attomey's Office