HomeMy WebLinkAboutExhibit 28 - August 29 Presentation1
Conditional Use Permit for
Shelter and Tiny Shelter/RV Park
Brent A. Butler, AICP, Chief Strategy Officer
Community Development Department
August 29, 2023
Applicant: Olympic Peninsula
Community Action Programs (OlyCAP)
Project Name: Caswell-Brown Village
2
Mission Statement
"To preserve and enhance
the quality of life in
Jefferson County by
promoting a vibrant
economy, sound
communities, and a
healthy environment."
1)Project Description
2)Phasing Plan
3)Permits Required
4)Exhibits
5)Criteria
6)Conditions of Approval
7)Comments
8)Final Recommendations
Agenda
3
Conditional Use Permit
Emergency Shelter (new 11,830 sf2 building)
40 spaces for Tiny Shelters/RVs (existing temporary use)
PROJECT DESCRIPTION
Staff Report Figure 10 –Emergency Shelter
4
5
Staff Report Figure 11 –Existing Temporary Use
40-Space Tiny Shelter/RV Park
6
Contextual
Overview
7
Three Principal Phases: What? When? Where? Why?
PHASING PLAN
8
Figure 2:
Phasing Plan
9
Three Principal Phases: What? When? Where? Why?
PERMITS REQUIRED
10
WHAT: Permitting included: Clearing, excavating, grading, utilities, road approach, addressing per JCC 18.20.385
•addressing (ADR2021-00142) to ensure that first responders could easily find the site;
•stormwater management (ZON2021-00060) to ensure that surface water is adequately managed;
•septic system technical support (OTH2021-00017) and approval (SEP2021-00229)
•adequacy of the septic system; access (RAP2021-00099)
•safe access to the site by users, visitors and others;
•utility placement (UTL2022-00029) to provide onsite utilities;
•septic operation and management (SOM2023-00045)
*correction to staff report page 9 (40 spaces approved in phase 1)
Applicant Received Permits Exhibit 5 –identifies permits received
Permits Required: When? Where? Why?
Existing temporary use
When –phase 1 (removed people/households from Fairgrounds)
Where –phase 1 (Initially sited in the upper site, moved to lower site)
Why –phase 1 (permitted through Jefferson County Code 18.20.385 &
15.05.065 Construction and life safety requirements for temporary
housing facilities permitted under JCC 18.20.385.
11
Permits Required
•CUP –Type III
•SEPA Review –MDNS (public facilities)
•Public Services
•Public Works (commercial stormwater review, road access, grading, clearing, utilities)
•Community Development
•Building Permit for new emergency shelter structure
•Tiny Shelters (NFPA regulations/ Not Appendix Q –Tiny Homes) regulations
•Environmental Public Health (sewage, solid waste, food service)
12
13
What are they and how do they inform the criteria?
EXHIBIT LIST
Exhibits –Available Online
14
15
Criteria
Conditions of Approval
Criteria 1 -The conditional use is harmonious and appropriate in design,
character and appearance with the existing or intended character and quality
of development in the vicinity of the subject property and with the physical
characteristics of the subject property;
•Structure Harmonious –RR 1:20
•40 Space Park (consistent with
other nearby uses (eg.Seabreeze))
•Forested to south and east
•Northwest (Larry Scott Trail)
16
Criteria 2 -The conditional use will be served by adequate infrastructure including
roads, fire protection, water, wastewater disposal, and storm water control;
17
•CUP –Type III
(Conditions 1 & 2)
•SEPA Review –MDNS (public facilities)
•Public Services –(Conditions 3 –7 and 31-35)
•Public Works (commercial stormwater review, road access, grading, clearing, utilities)
(Conditions 3 & 8 to 12)
•Community Development
•Building Permit for new emergency shelter structure
•Tiny Shelters (NFPA regulations/ Not Appendix Q –Tiny Homes) regulations
(Conditions 13 –30 & 35)
•Environmental Public Health (sewage, solid waste, food service)
(Conditions 36, 37, 38)
Criteria 3 -The conditional use will not be materially detrimental to uses or
property in the vicinity of the subject parcel;
Applicant implements
CPTED’s three elements including: 1) Territoriality, 2) Surveillance and 3) Access Control.
1)Occupants ownership of surrounding space by plantings
2)General maintenance (site inspections) verified, and annual
3)Lines of sight (architect can discuss)
4)Lighting
5)Access
6) Plans required –condition number 6
•Safety and Security Plan
•Operations Plan,
•Transportation Plan
•Perimeter Plan
•Communications and Coordination Plan
18
Criteria 4 -The conditional use will not introduce noise, smoke, dust, fumes,
vibrations, odors, or other conditions or which unreasonably impact existing
uses in the vicinity of the subject parcel;
•Traffic Impacts (see letter –Exhibit 13)
•Conditions included:
Recommended Conditional Number 8 -All required permits shall be obtained prior to commencement of land clearing,
construction and/or occupancy for phase III
Recommended Condition Number 9 -Construction plans and profiles for all roads, storm drainage facilities and
appurtenances prepared by the developer’s engineer shall be submitted to Jefferson County for review and acceptance.
No construction shall be started prior to said plan acceptance.
19
Criteria 5 -The location, size, and height of buildings, structures, walls and
fences, and screening vegetation for the conditional use will not unreasonably
interfere with allowable development or use of neighboring properties;
20
TABLE 2: COMPARATIVE ANALYSIS OF PROPOSAL AND UDC
Unified Development Code UDC Requirements or CUP approval guidelines Proposed by Applicant
Zoning / Use Category •Rural Residential
•Density: 1 Dwelling Unit for 20 Acres•Table 3-1, JCC 18.15.040 Categories of land use
•Discretionary use pursuant to Table 3-1 for all Unnamed institutional uses, as
this Public Purpose Facilities would be classified
No changes to zoning
Number of Residents Until city sewer is available, the approved septic permit determines maximum load, as set
forth below
1)Shelter: 50 beds / up to 75 persons or the approved septic permit capacity,
whichever is less
2)40-Space Park/ up to 75 persons or the septic capacity, whichever is less.
(Existing capacity is 48 people pursuant to SEP2021-00229, as set forth in the
Augusta 8, 2023 Environmental Review Memorandum issued using SEPA’s
substantive authority )
40 bed shelter with (50 beds would be the maximum capacity by including a double bed or
bunk bed in the three one-bedroom units, and a bunk or double in the two emergency
shelter rooms)
Site Area 20 acres, Tax Parcel: 001162001 21.81 acres (source: Assessor’s Website)
Lot Coverage Not Applicable
Impervious Surface 25%IMPERVIOUS COVERAGE: 17% (source: Phase 2 site plan as built 5-10-2023)
Building Height 35 feet 23 feet 8 inches pursuant to Attachment A
Setbacks
Side (west)
Front (south)
Rear (north)
Side (east)
35
35
35
100
305 feet
507 feet
568 feet
428 feet
Minimum Front and Road Setbacks
Highway 20 (principal arterial)
Mill Road (formerly Glen Cove Road)50
20 (local access road)
305 feet
428 feet
Landscaping Must be in conformance with recommendations in Exhibit 11, CPTED Best Management
Practices
Implementation of CPTED Best Practices identified as a condition of approval
Parking Spaces Required for Unnamed institutional uses Determined by the Administrator 27 and 19 spaces for the shelter and 40-lot park respectively
Criteria 6 -The pedestrian and vehicular traffic associated with the
conditional use will not be hazardous to existing and anticipated traffic in the
vicinity of the subject parcel;
21
•See Exhibit 13 –PBS Letter (transportation engineer)
•See Site Context –Larry Scott Trail
Criteria 7 -The conditional use complies with all other applicable criteria and
standards of this Code and any other applicable local, state or federal law;
and more specifically, conforms to the standards contained in 18.20 and
18.30 of this Code;
Criteria 8 -The proposed conditional use will not result in the siting of an
incompatible use adjacent to an airport or airfield;
Criteria 9 -The conditional use will not cause significant adverse impacts on
the human or natural environments that cannot be mitigated through
conditions of approval;
22
•See table referenced in criteria 6 and there’s no incompatibility with the airport or field, as it’s far enough away to avoid any potential for interference with operations. All the applicable conditions reduce, eliminate and avoid any impacts per criteria 9.
23
Criteria 10 -The conditional use has merit and value for the community as a
whole; -
Criteria 11 -The conditional use is consistent with all relevant goals and
policies of the Jefferson County Comprehensive Plan; and
Goal HS-G-1 Encourage and support efforts to increase
housing availability for county residents of all income
groups.
Goal HS-G-2 Promote a variety of housing choices
throughout the county with innovative land use practices,
community redevelopment strategies, development
standards, design techniques, and building and
infrastructure permit requirements.
Policy HS-P-2.1 Explore regulatory opportunities that help
minimize costs to developing affordable housing while
ensuring that public health, safety, and environmental
quality standards are not compromised.
The application responds to an emergency
highlighted by the data referenced in the staff
report, namely:
1)the Washington Center for Real Estate
Research
2)Making Homelessness a Singular
Occurrence
Permits Required
•CUP –Type III
(Conditions 1 & 2)
•SEPA Review –MDNS (public facilities)
•Public Services –(Conditions 3 –7 and 31-35)
•Public Works (commercial stormwater review, road access, grading, clearing, utilities)
(Conditions 3 & 8 to 12)
•Community Development
•Building Permit for new emergency shelter structure
•Tiny Shelters (NFPA regulations/ Not Appendix Q –Tiny Homes) regulations
(Conditions 13 –30 & 35)
•Environmental Public Health (sewage, solid waste, food service)
(Conditions 36, 37, 38)
24
25
COMMENTS
COMMENTS –After supplemental memorandum/report
Revised Condition Number 38
The Applicant’s CUP permit is conditioned upon Jefferson County
Environmental Public Health having already permitted and approved for
use a septic system to serve the existing “40-lot Park.” The applicant
proposes constructing a new 50 bed shelter.The new shelter must be
served by a septic system that meets WAC246-272A, and is limited to 3500
gallons per day or 50 beds, which ever is smaller.
EJFR’s comments:
The proposed structure should comply with required permitting, review,
inspection and built to all applicable state and federal codes.
Furthermore, EJFR wants to ensure we have input of the building, design,
building type, ingress / egress, FDC / PIV, hydrant location, etc. We want
to provide the best access possible for emergency scenarios at the
facility.
26
QUESTIONS?
27