HomeMy WebLinkAboutChange Order No 4 Hadlock Sewer Department of Public Works
O Consent Agenda
Page 1 of 1
Jefferson County
Board of Commissioners
Agenda Request
To: Board of Commissioners
Mark McCauley, County Administrator
From: Monte Reinders, P.E., Public Works Director/County Engineer k.1 -
Agenda Date: December 11, 2023 �_
Subject: Change Order No. 4, Phase 1 - Site Prep., Earthwork and Service
Utilities for the Port Hadlock Sewer, Project No. 405-2114-0,
Commerce Project No. 22-96515-026
Statement of Issue: Change Order No. 4 with Seton Construction of Port Townsend,
Washington.
Analysis/Strategic Goals/Pro's Et Con's: This change order includes an increase in
cost to change the materials and improve the design detail for the low pressure sewer
cleanouts. The revised cleanout design changes were done to standardize the
cleanouts in order for the materials and installation methods to be consistent
throughout the sewer construction phases.
Fiscal Impact/Cost Benefit Analysis: The amount for Change Order No. 4 is
$21,213.40. The contract amount will increase from $1,550,086.52 to $1,571,299.92.
NOTE, the cost included 9.1% sales tax. The project is funded at 100% by the
Department of Commerce.
Recommendation: Public Works recommends that the Board authorize Change Order
No. 4 with Seton Construction, and return one original to Public Works for further
processing.
Department Contact: Samantha Harper, P.E., Project Manager, 385-9175.
Reviewe y:
s- -3
Mark McCauIeJJCounty Administrator Date
JEFFERSON COUNTY
Sheet 1 of 2 DEPARTMENT OF PUBLIC WORKS Change
4
Date: 11/15/2023 CHANGE ORDER Order No.
Ordered by County Engineer under terms of
Election 1-04.4 of the Standard Specifications
Contract No.
Change proposed by Contractor To:
Seton Construction
Endorsed by: Seton Construction,Inc. 4640 S. Discovery Rd.
Contractor Firm Name
Port Townsend, WA 98368
_.� Q_ 11/27/2023
�c
Signature &IFDate
President
Title
Consent given by Surety:(when required) Project Title Phase 1-Site Prep.,
Earthwork,and Service
By: Utilities for the PH Sewer
Attorney-in-fact Date
You are ordered to perform the following described work upon receipt of an approved copy of this change order:
The change clarified and revised the sewer cleanout materials which were not provided in the original cleanout
detail. The sewer cleanout detail(s)were revised in order to standardize the materials and configurations; to ensure
all the sewer cleanouts moving forward will be constructed consistently.
All work materials and measurement to be in accordance with the provisions of the standard specifications and
special provisions for the type of construction involved.
ORIGINAL CURRENT ESTIMATED ESTIMATED
CONTRACT CONTRACT NET CHANGE CONTRACT TOTAL
AMOUNT(incl.9.1%sales tax) AMOUNT(incl.9.1%sales tax) THIS ORDER(incl.9.1%sales tax) AFTER CHANGE(incl.9.1%sales tax)
$ 1,243,245.78 $ 1,550,086.S2 $21,213.40 $ 1,571,299.92
ORIGINAL CURRENT CONTRACTTIME NEW CONTRACT
CONTRACTTIME CONTRACT TIME CHANGE(Add/Del) TIME
100 112 2 114
APPROVA RECOMMENDED APPROVAL RECO ENDED
6 Z3
1
Project Manager Date County Engineer Date
APPROVAL RECOMMENDED APPROVED
El
Engineering Services Manager Date Chair,Jefferson County Commissioners Date
JEFFERSON COUNTY Contract Nc 405-2114-0
Sheet 2 of 2 DEPARTMENT OF PUBLIC WORKS
Change
Date: 11/15/2023 CHANGE ORDER ESTIMATE Order No. 4
ESTIMATED ESTIMATED
ITEM DESCRIPTION UNIT UNIT QUANTITY AMOUNT
NO. MEASURE PRICE CHANGE CHANGE
NEW ITEMS
25 R1 Pressure Sewer Cleanout EA $7,861.00 4 $31,444.00
New Item Total $31,444.00
EXISTING ITEMS DELETED QUANTITIES
25 Pressure Sewer Cleanout EA $3,000 4 ($12,000.00)
Existing Items Deleted Quantities
Total ($12,000.00)
EXISTING ITEMS ADDED QUANTITIES
$0.00
Existing Items Added Quantities $0.00
ESTIMATED NET CHANGE SUBTOTAL: $19,444.00
9.1% Sales Tax $1,769.40
ESTIMATED NET CHANGE TOTAL: $21,213.40
JEFFERSON COUNTY
Sheet 1 of 2 DEPARTMENT OF PUBLIC WORKS Change
Date: 11/15/2023 CHANGE ORDER Order No. 4
Ordered by County Engineer under terms of
❑X Section 1-04.4 of the Standard Specifications
Contract No.
Change proposed by Contractor To:
Seton Construction
Endorsed by: Seton Construction,Inc. 4640 S. Discovery Rd.
Contractor Firm Name Port Townsend, WA 98368
11/27/2023
Signature Date
President
Title
Consent given by Surety:(when required) Project Title Phase 1-Site Prep.,
Earthwork,and Service
By: Utilities for the PH Sewer
Attorney-in-fact Date
You are ordered to perform the following described work upon receipt of an approved copy of this change order:
The change clarified and revised the sewer cleanout materials which were not provided in the original cleanout
detail. The sewer cleanout detail(s)were revised in order to standardize the materials and configurations; to ensure
all the sewer cleanouts moving forward will be constructed consistently.
All work materials and measurement to be in accordance with the provisions of the standard specifications and
special provisions for the type of construction involved.
ORIGINAL CURRENT ESTIMATED ESTIMATED
CONTRACT CONTRACT NET CHANGE CONTRACT TOTAL
AMOUNT(incl.9.1%sales tax) AMOUNT(incl.9.1%sales tax) THIS ORDER(incl.9.1%sales tax) AFTER CHANGE(incl.9.1%sales tax)
$ 1,243,245.78 $ 1,550,086.52 $21,213.40 $ 1,571,299.92
ORIGINAL CURRENT CONTRACT TIME NEW CONTRACT
CONTRACT TIME CONTRACTTIME CHANGE(Add/Del) TIME
100 112 2 114
ROVA RECOMMENDED APPROVAL RECO ENDED
b
� l
Project Manager Date County Engineer Date
APPROVAL RECOMMENDED APPROVED
❑ 1
Engineering Services Manager Date Chair,Jefferson County Commissioners Date
JEFFERSON COUNTY Contract No 405-2114-0
Sheet 2 of 2 DEPARTMENT OF PUBLIC WORKS
Change
Date: 11/15/2023 CHANGE ORDER ESTIMATE Order No. 4
ESTIMATED ESTIMATED
ITEM DESCRIPTION UNIT UNIT QUANTITY AMOUNT
N0. MEASURE PRICE CHANGE CHANGE
NEW ITEMS
25 R1 Pressure Sewer Cleanout EA $7,861.00 4 $31,444.00
New Item Total $31,444.00
EXISTING ITEMS DELETED QUANTITIES
25 Pressure Sewer Cleanout EA $3,000 4 ($12,000.00)
Existing Items Deleted Quantities
Total ($12,000.00)
EXISTING ITEMS ADDED QUANTITIES
$0.00
Existing Items Added Quantities $0.00
ESTIMATED NET CHANGE SUBTOTAL: $19,444.00
9.1% Sales Tax $1,769.40
ESTIMATED NET CHANGE TOTAL: $21,213.40