Creating a County project designated as x RESOLUTION NO 2 7—2 4
Olympic Discovery Trail—Puget Sound to Pacific x
IT IS HEREBY RESOLVED that the Olympic Discovery Trail,County Road No. 850200, be improved as
follows:
The Olympic Discovery Trail(ODT)—Puget Sound to Pacific is included in the officially adopted
2024-2029 Transportation Improvement Program(TIP)as Project No. 15.The project will perform
preliminary engineering on five(5)connections of the ODT.
IT IS FURTHER RESOLVED that an appropriation from the officially adopted road fund budget and based on
the County Engineer's estimate is hereby made in the amounts and for the purposes shown:
PURPOSE FUNDING
Previous
Appropriation Present Appropriation
Rebuilding American Infrastructure with Road Total
Sustainability and Equity(RAISE)Grant Fund
Preliminary Engineering $0 $2,080,000 $0 $2,080,000
•
TOTAL $0 $2,080,000 $0 $2,080,000
X This project is included in the officially adopted annual road program as Item No. 14 .
The project is hereby made a part of the officially adopted annual road program in accordance with
R.C.W. 36.81.130.
IT IS FURTHER RESOLVED that:
X The construction is to be accomplished by contract in accordance with R.C.W. 36.77.020 et. seq.
The construction is to be accomplished by County forces in accordance with R.C.W. 36.77.065 and
W.A.C. 136.18.PASSED AND ADOPTED THIS ��` DAY OF /��//�
li , /2 (-/.
JEFFERSON COUNTY
F F EF- BOARD OF COMMISSIONERS
Go M MSS;. ti �'•
SEAL: A ' v" /2 G
= -i : m- Z
Ti --I= K Dean, District 1
• •
AITEST: 'yaShiNG�a O?��,
Na� auoaa`�
e i • our,District 2
git4)1
Carolyn allaway,CMC /G Brotherton,District 3
Clerk of the Board
Department of Public Works
O Consent Agenda
Page 1 of 1
Jefferson County
Board of Commissioners
Agenda Request
To: Board of Commissioners
Mark McCauley, County Administrator
From: Monte Reinders, P.E., Public Works Director/County Engineer
Agenda Date: May 6, 2024
Subject: Resolution to Create County Project
Olympic Discovery Trail (ODT) - Puget Sound to Pacific (PS2P),
County Road No. 850200
Statement of Issue: Create a county project known as the Olympic Discovery Trail
(ODT) - Puget Sound to Pacific (PS2P).
Analysis/Strategic Goals/Pro's £t Con's: The ODT is a shared use path planned to run 27
miles from the City of Port Townsend to Clallam County. This project is #15 on the
Transportation Improvement Program, and #14 on the Annual Construction Program. The
next step to complete the ODT includes the design of 7.5 miles of gaps between existing
trail segments. ODT connection to Kitsap County is undefined, and needs a route
alternatives study that recommends a preferred alignment. Public Works has been
awarded funding for this project through the US Department of Transportation (USDOT)
Rebuilding American Infrastructure with Sustainability and Equity (RAISE) discretionary
grant program. These funds cannot be used for right of way acquisition or for
construction.
Fiscal Impact/Cost Benefit Analysis: The total estimated project cost is $2,080,000,
which will be funded at 100% by the US Department of Transportation (USDOT)
Rebuilding America Infrastructure with Sustainability and Equity (RAISE) discretionary
grant program.
Recommendation: The Board is requested to sign one original of the Resolution to
Create County Project.
Department Contact: John Fleming, P.E. Project Manager, 385-9217.