July 1, 1994
Mr. Ray Welch
Pope Resources
781 Walker Way
Port Ludlow, WA 98365
RE: SUMMARY LE I1 ER
GEOTECHNICAL CONSULTATION AND
CONSTRUCTION OBSERVATION SERVICES
INN AT PORT LUDLOW TOWNHOMES
PORT LUDLOW, WASHINGTON
Dear Mr. Welch:
This letter presents a summary of our observations and conclusions regarding the
installation of piles for support of five townhome buildings at the Inn at Port Ludlow
development. Landau Associates received your verbal authorization to proceed with our
services on June 7, 1994. Our services included:
• Performing a dynamic analysis to calculate appropriate pile driving criteria,
including minimum blow count and refusal criteria
• Observing the installation of the piles and logging each pile installation with
a field log that recorded blow count information, pile tip elevation, comments
and observations regarding obstructions encountered, and deviation of piles
from planned locations
• Preparing this summary letter.
A total of 345 creosote pressure-treated timber piles were driven during the period from
June 1.5 through June 28, 1994, by the pile subcontractor, General Construction. Piles ranging
from about 25 to 50 feet in length were delivered to the job site; most of the pile lengths were
about 25 feet. After driving a 50-foot pile to satisfactory driving resistance, the contractor cut
off the remainder for use as a second pile.
All of the piles, with the exception of one pile driven at an incorrectly-staked pile
location, and subsequently not used, achieved the minimum blow count and (typically) the
embedment criteria Landau Associates recommended for this project. Landau Associates
recommended a minimum of 25 blows per foot or 10 blows for the last 3 inches of driving
07101/94 D:11\TPOCSTROJECTs\ SC.16T11165.RYI
WORLD TRADE CENTER•3600 PORT OFTACOMA ROAD•SUITE 501 •TACOMA.WA 98-14•(1-06i 916-1403•FAX('061 9'6-15 31
EDMONDS: i2061775-(1t707.F\\ 201ii„S-(i-lim/SPOK:ANE(50(1327 o)737•F-AS i51i9i 3'7-9h91
(provided there were at least 20 blows for the preceding foot of driving). In addition to the
minimum blow count criteria, a minimum embedment of 3 feet into medium-dense to dense
native soil was recommended. At some locations, the piles encountered dense to very dense
native soil and the driving resistance increased well above the recommended minimum blow
count, hence the recommended minimum embedment was not achieved. However, in these
cases, the piles were considered adequate and suitable for their intended use because of the
high driving resistance developed.
In general, the piles were installed in a routine fashion at staked locations. Some of the
piles encountered obstructions during driving. The effect of the obstructions ranged from
causing the piles to gradually deflect off staked locations, to causing damage to the piles. At
those locations where the piles deflected more than a 4-inch tolerance from plan locations, the
general contractor, Walsh Construction, was informed so that Walsh Construction could inform
the project structural engineer (Ed Johnson) and request direction regarding any necessary
revisions to the grade beam reinforcement details. At those locations where the-piles were
damaged and rendered unusable, the piles were either extracted and replaced at the plan
location or supplemental piles were installed adjacent to the broken piles at the direction of the
structural engineer.
In addition to requesting direction from the structural engineer regarding piles that
deviated from staked locations, we understand the contractor will also contact the structural
engineer regarding piles whose heads were driven below cutoff elevation. These were piles
that did not achieve the minimum driving resistance until the pile head was driven below
planned cutoff elevation.
Information on each pile is summarized in Table 1; the piles are designated by their
locations relative to a building line grid system developed in the field by Walsh Construction
and Landau Associates. A convention of alphabetic grid lines extending from left to right and
numeric lines extending from top to bottom of the pile layout Foundation Plan was used for
each building. These grid lines were imposed along the centerline of each grade beam. We
have retained individual field pile driving logs in our files.
Following is a summary of pile-driving activities at each building location and at the
proposed "waterfall" location.
07/01/94 D:IWPDOCSIPROIECISNISC116700165.RPT 2
LANDAU ASSOCIATES,INC.
-Building 100
Prior to pile installation, the contractor removed existing concrete and brick foundations
around the former smokestack footing. Most of the building 100 area was excavated about 4
feet below adjacent site grade. The first 18 piles installed at this location were emplaced with
the pile driving rig adjacent to.the excavation. The remaining 20 piles were driven with the
pile driving rig in the excavation. A total of 38 piles were driven during the period from June
23 to June 27, 1994. This total includes one extra pile installed adjacent to'a pile that broke on
June 23. That pile was replaced at the direction of the structural engineer with one to the east
of the broken pile. About 3 piles were driven until their heads were below what we
understood to be the cutoff elevation.
Building 200
A total of 86 piles were driven at this location on June 15 and 16, 1994. Problems
encountered included an obstruction at 3 feet depth at one pile location. The pile tip was
broken by the obstruction. The pile was extracted, the pile tip trimmed, relocated 2 feet north
of-the plan location by Ted Wilson, Superintendent for Walsh Construction, and successfully
redriven. Two piles did not achieve satisfactory driving resistance during their initial
installation; thosepiles were later redriven to-satisfactory driving resistance with a mandrel.
The pile heads were at or just below cutoff elevation after driving.
Building 300
A total of 82 piles were driven at this location during the period June 16 through June
20, 1994. One pile encountered an obstruction when the pile was embedded at 17 feet below
ground surface and broke near the ground surface before satisfactory driving resistance was
achieved. The broken pile was extracted and the obstruction was excavated, using a hydraulic
excavator. The pile was replaced at the plan location with a new pile that was driven to
satisfactory resistance and embedment. Two piles did not achieve satisfactory resistance during
their initial installation; they were redriven to satisfactory resistance using a mandrel. The
heads of these 2 piles appeared to be at or above cutoff elevation after driving. One pile
achieved a final blow count of 10 blows per foot and was not redriven to the recommended
minimum blow count of 25 blows per foot. From conversations with the project structural
engineer, we understand a capacity of 15 tons is required for that pile. Our evaluation of the
pile driving data indicates this pile will have sufficient capacity for its intended loading.
07/01/94 D:IWPDOCSIPROJECTSIMISC1167x01.55.KPr 3
LANDAU ASSOCIATES,INC.
-
Building 400
A total of 77 piles were installed on June 27 and 28, 1994. In addition to the 77 piles
placed at the plan locations, one pile was driven to an embedment of 12 feet at an incorrectly-
staked pile location. The pile rig unsuccessfully attempted to extract that pile, which was cut
off at the ground surface and another pile installed at the proper location. Other problems
included one pile that moved about 7 inches off of the staked location during driving and did
not, at first, achieve satisfactory driving resistance. This pile was later redriven with a mandrel
to satisfactory resistance, although the pile head was driven to approximately 3 feet below
ground surface (about 11/2 feet below proposed cutoff elevation). Another pile deviated
approximately 8 inches off of plan location, apparently from encountering an obstruction
during driving. Another pile broke at the ground surface and 4 feet above ground surface at
the very end of driving. The pile did not exhibit behavior that would indicate it was damaged
below the break at the ground surface and, according to a representative of Walsh
Construction, this pile could be successfully trimmed below the lower break and incorporated
satisfactorily into the pile cap. The piles that deviated from plan location were identified to
Walsh Construction, who inform the structural engineer so that appropriate revisions, if
necessary, can be made to the pile caps.
Building 500
A total of 57 piles were driven satisfactorily at the building 500 location between June
20 and 23, 1994. There were no apparent problems with any of these piles.
Waterfall Piles
Four piles were installed for proposed waterfall installations. Two piles were located
outside of the north end of building 500, and 2 piles were located between the southwest
corner of building 500 and the Inn at Port Ludlow Hotel, currently under construction. These
four piles were installed without incident.
In summary, it is our opinion that all piles were installed in general accordance with the
project plans and specifications and our recommendations (except as noted above) and are
suitable for support of the proposed structures.
07/01194 D:IWPDOCSWROJECrS1MISC116700165.RPT 4
LANDAU ASSOCIATES,INC.
We trust this summary letter meets your needs. We have enjoyed serving you on this
interesting project. If you have any questions, please contact us at (206) 926-2493.
LANDAU ASSOCIATES, INC.
By:
d,-.. - d. J,--.......,.._
.",--, ',, , J. C . -
William D. Evans, CPG
- -/ �u ,I'l' 11 Project Manager
,91
1 : ' - ,l- x and
L` %Oi\JALG`
tep en J. oover, P.E.
' Project Engineer
WDE/SJC/mlm
No. 176001.65
attachment: Table 1