Jefferson County
Board of Commissioners
Agenda Request
To: Board of Commissioners
Mark McCauley, County Administrator
From: Monte Reinders, P.E., Public Works Director/County Engineeo�
Agenda Date: June 17, 2024
Subject: Change Order No. 1, for Center Road 211 Overlay Project
Project No. 1802096,
County Road No. 931507, CRAB R.A.P. Project No. 1622-01
Statement if Issue: Change Order No. 1 with Lakeside Industries, Inc. of Port
Angeles, Washington.
Analysis/Strategic Goals/Pro's If Con's: This change order consists of 4 parts:
Part 1: Change of Planing and Paving Width to completely remove the existing chip
seal surface from the roadway
Part 2: Crack Sealing to seal the cracks in the existing surface of the asphalt shoulders
with Hot Applied Sealant for Bituminous Pavement.
Part 3: Culvert Pipe Repair of an existing culvert in the north-bound lane of Center
Road at sta. 761+30 which is seeping stormwater upward and onto the newly planed
asphalt roadway surface.
Part 4: Deletion of Item 18 Plastic Drainage Markers from the contract; this work to
be done by County Forces.
Fiscal Impact/Cost Benefit Analysis: Change Order No. 1 adds $58,983.23 to the
existing contract amount of $1,112,583.65 for a revised contract total amount of
$1,171,566.88 and adds 0 Working Days. This project is funded at 100% by a County
Road Administration Board (CRAB), Rural Arterial Program (R.A.P.) State grant.
Recommendation: Public Works recommends that the Board authorize Change Order
No. 1 with Lakeside Industries, Inc., and return two originals to Public Works for
further processing.
Department Contact: John Wayand, Project Manager, 385-9377.
Reviewed B .
,6
Mark M auley, County Administrator Date
JEFFERSON COUNTY
Sheet I of 5 DEPARTMENT OF PUBLIC WORKS Change
Order No. 1
Date: 6/3/2024 CHANGE ORDER 1(PARTS 1,2, 3,41)
Ordered by County Engineer under terms of
❑X Section]-04.4 of the Standard Specifications
Contnet No.
Change proposed by Contractor To:
Lakeside Industries,Inc.
Endorsed by: Lakeside Industries Inc. P.O.Box 728.
� „ Port Angeles,WA.98362
Contractor Firm Name
Signa(ure Date
Title
Consent given bySuW7 when required) Project Title
Center Road 2R Overlay
By_ Project No.1802096
Anorn ,(act Date
You are ordered to pi rfarm the following described work upon receipt of an approved copy of this change order:
PART 1:CHANGE OF PLANING AND PAVING WIDTH
This change is being made to completely remove the existing chip seal surface from the roadway.
Existing Item Id Planing Bituminous Pavement,SY
This change order provides for additional quantities of Planing Bituminous Pavement for an increase in total planing
width from 24'wide to 25'wide,from sta.543+60 to sta.668+00. This change requires an additional 1,293.33 SY of
planing.
Estimated cost is:$2,728.93
Change in Contract Time:0 additional Working Days
Existing Item 12 HMA CL 1/2 In.PG 58H 22,TON
This change ordgr provides for additional quantities of HMA Cl.1/2 In. PG 58H-22(Hot Mix Asphalt)for an increase in
total width from 24'wide to 25'wide,from sta.543+60 to sta.658+00 south-bound lane and from sta.543+60 to
657+50 north-bound lane. This change requires an additional 173.34 TONS of HMA.
Estimated cost is:$16,467.30
Change in Contract Time:0 additional Working Days
Existing Item 2 Proiect Temporary Traffic Control,LS
This change ordI r provides for additional Project Temporary Traffic Control to accomplish the increase in total width
from 24'wide to 25'wide,from sta.543+60 to sta.658+00 south-bound lane and from sta.543+60 to 657+50 north-
bound lane. This change requires an additional$2,696.00 for traffic control.
Estimated cost is:$2,696.00
Change in Contract Time:0 additional Working Days
Change Order 1,Part 1 Summary:
Estimated Cost:
$2,728.93 Planing Bituminous Pavement
$16,467.30 HMA CL.1/2 In.PG 58H-22
$2,696.00 Protect Temporary Traffic Control
$21,892.23 itotal Estimated Net Cost Change
Estimated Contract Time:
0 Working Days Planing Bituminous Pavement
0 Working Days HMA CL. 1/2 In.PG 58H-22
0 Working Days Protect Temporary Traffic Control
0 Working Days Total Estimated Net Working Days Change
Sheet 2 of 5
PART 2:Crack Sealing
° This change is tieing made to seal the cracks in the existing surface of the asphalt shoulders.
New Item 26 Crack Sealing,LS.
This change order adds the new item"Item 26 Crack Sealing,L.S."per Standard Specification 1-04.4. This change order
provides for sealing the cracks in the existing asphalt shoulders with Hot Applied Sealant for Bituminous Pavement.
The crack sealing will occur on both the north-bound and south-bound shoulders for the entire project length from sta.
543+60 to sta.667+22,for an estimated 3,225 LF.of cracks. This change order also includes shoulder sweeping and
traffic control. This change requires an additional$26,325.00 L.S.
Estimated cost is:$26,325.00
Change In Contract Time:0 additional Working Days
Change Order 1,Part 2 Summary-,
Estimated Cost:
$26,325'00 Total Estimated Net Cost Change
Estimated Contract Time:
0 Working Days Total Estimated Net Working Days Change
i
PART 3:Culvert Pipe Repair
This change is tieing made to repair an existing culvert in the north-bound lane of Center Road at sta.761+30 which is
seeping stormwater upward and onto the newly planed asphalt roadway surface.
New Item 27 Culvert Pipe Repair.LS.
This change order adds the new item"Item 27 Culvert Pipe Repair,L.S."per Standard Specification 1-04.4. This change
order provides for asphalt sawcutting,excavation and removal of the existing broken concrete culvert pipe, installation
of 13 L.F.of new 6"diam.PVC culvert drain pipe,Crushed Surfacing Base Course bedding and backfill rock, 1.5 tons of
4"thick HMA pavement repair,sweeping,and traffic control. This change requires an additional$17,262.00 L.S.
Estimated cost�is:$17,262.00
Change in Contract Time:0 additional Working Days
Change Order 1,Part 3 Summary:
Estimated Cost:
$17,262.00 Total Estimated Net Cost Change
Estimated Contract Time:
0 Working Daiys Total Estimated Net Working Days Change
PART 4:Plastic Drainage Marking
This change is being made in order to remove installation of plastic drainage markers from the contract and have
Jefferson County forces install the plastic drainage markers in conjuction with installation of plastic culvert numbers.
Existing Item 18 Plastic Drainage Marking,EA.
This change order deletes the existing"item 18 Plastic Drainage Marking,EA."per Standard Specification 1-04.4.
Removing this item from the contract will allow earlier work completion and close-out of the contract. Jefferson
County forces will be used to install the plastic drainage markers and the plastic culvert numbers. This change reduces
the contract amount by$6,496.00.
Estimated Cost.-$6,496.00
Change in Contract Time:0 reduction in Working Days.
Change Order 1,Part 4 Summary:
Estimated Cost:
-$6,496.00 Total Estimated Net Cost Change
Estimated Contract Time:
0 Working Days Total Estimated Net Working Days Change
i
Sheet 3 of 5
Total Change Order 1 Summary:
Estimated Cost;
$21,892.23 Part 1:Change of Planing and Paving Width
$26,325.00 Part 2:Crack Sealing
$17,262.00 Part 3:Culvert Pipe Repair
-%A96,00 Part 4:Plastic Drainage Marking
$58,983.23 Total Estimated Net Cost Change
Estimated Contract Time:
0 Working Day Part 1: Change of Planing and Paving Width
0 Working Days Part 2: Crack Sealing
0 Working Days Part 3:Culvert Pipe Repair
0 Working Days Part 4:Plastic Drainage Marking
0 Working Days Total Estimated Net Working Days Change
All work materials and measurement to he in accordance with the provisions of the standard specifications and
s ecial. rovisions for;the type of construction involved.
ORIGINAL CURRENT ESTIMATED ESTIMATED
CONTRACT CONTRACT NET CHANGE CONTRACT TOTAL
AMOUNT AMOUNT TIES ORDER AFTERCHANGE
S1,112,583.65 $1,112,583.65 $58,983.23 $1,171,566.88
ORIGINAL CURRENT CONTRACT TIME NEW CONTRACT
CONTRACT TIME CONTRACT TIME CHANGE(Add/Del) TIME
25 Working Days) 25 Working Days 0 Working Days 25 Working days
APPROVAL RECOMMENDED APPROVAL MMENDE
P-Jeet J4Emrager Date County F-gineer Date
APPROVAL RECOMMENIAD APPROVED
Bngineerieg Servings Manager Dole Chair.Jefferson Cormty Cmm duldnav Date
JEFFERSON COUNTY I I ContraotNo. 1 I I I 1802096
Sheet 4 of 5 DEPARTMENT OF PUBLIC WORKS ! I I I
Change I
I
i
Date: I 6/3lZ024 CHANGE ORDER 1(PARTS 1,2,3,and 4)ESTIMATE Order No. l 1
TEEM GROUP DESCRIPTION EXISTING EXISTING EXISTING EXISTING NEW NEW NEW NEW
-- —---NEW
- --- -- -
"— —NO NO UNIT UNIT TOTAL TOTAL UNIT UNrr TOTAL TIOTAL AMOUNT
MEASURE PRICE QUANTITY AMOUNT MEASURE PRICE QUANTITY AMOUNT CHANGE
PART 1:CHANGE OF PLANING AND PAVING WIDTH
EXISTING ITEM
Planing Bituminous
10 N/A Pavement SY $2.11 60000.00 $126,600.00 SY $2.11 61293.33 $129,328.93 $2,728.93
Total Item 10 SY $2.11 60000.00 $126,600.00 SY $2.11 61293.33 $129,328.93 $2,728.93
HMA CL.1/2 In.PG
12 N/A 5SH-22 TON $95.00 8185.00 $777,575.00 TON $95.00 8358.34 $794,042.30 $16,467.30
Total Item 12 TON $95.00 9185.00 $777,575.00 TON $95.00 8358.34 $794,042.30 $16,467.30
Project Temporary
21 N/A Traffic Control L.S. $55,000.00 1.00 S55,000.00 L.S. $57,696.00 1.00 $57,696.00 $2,696.00
Total Item 21 L.S. $55,000.00 1.00 $55,000.00 L.S. $57.696.00 1.00 $57,696.00 $2,696.00
TOTAL PART 1 $959,175.00 $981,067.23 $21,892.23
PART 2:CRACK SEALING
NEW ITEM
26 N/A Crack Sealing N/A $0.00 0.00 $0.00 L.S. $26,325.00 1.00 $26,325.00 $26,325.00
Total Item 26 N/A $0.00 0.00 $0.00 L.S. 1 $26,325.00 1.00 $26,325.00 $26,325.00
TOTAL PART 2 $0.00 $26.325.00 $26.325.00
I I
Sheet 5 of 5
ITEM GROUP DESCRIPTION EXISTING EXISTING EXISTING EXISTING NEW NEW NEW NEW
NO NO. UNIT UNIT TOTAL TOTAL UNIT UNIT TOTAL TOOTAL AMOUNT
MEASURE PRICE QUANTITY AMOUNT MEASURE PRICE QUANTITY AMOUNT CHANGE
PART 3:CULVERT PIPE REPAIR
NEW ITEM
27 N/A Culvert Pipe Repair NIA $0.00 0.00 $0.00 L.S. $17,262.00 1.00 $17,262.00 $17,262.00
Total Item27 NIA $0.00 0.00 $0.00 L.S. $17,262.00 1.00 $17,262.00 $17,262.00
i i i i i
TOTAL PART 3 $0.00 $17,262.00 $17,262.00
PART 4:PLASTIC DRAINAGE MARKING
EXISTING rMM
Plastic Drainage
18 NIA Marking EA. $112.00 58.00 $6,496.00 EA. $112.00 -58.00 $0.00 -$6,496.00
Total Item 18 N/A $112.00 58.00 $6,496.00 EA. $112.00 -58.00 $0.00 -$6.496.00
TOTAL PART 4 { $0.00 $0.00 -S&496.00
i
i CHANGE ORDER 1(PARTS 1,2,3,and 4)ESTIMATED NET CHANGE TOTAL: $58,983.23