Loading...
HomeMy WebLinkAboutInterwest Construction Change Order No. 3 Phase 2 Water Reclamation Plant for the Port Hadlock UGA - 080524 JEFFERSON COUNTY Sheet 1 of 2 DEPARTMENT OF PUBLIC WORKS Change Date 7/19/2024 CHANGE ORDER order No. Ordered by County Engineer under terms of EArticle 9 and 11 of the General and Supplemental Conditions ,,115.2 I.l,l 11 Contract No. Change proposed by Contractor To: Interwest Construction Endorsed by: t"r\,..,-rs-y 5� �r 4575 Fey Rd Contractor Firm Name Port Angeles,WA 98363 S/g o w!f t e Date r ' Yr,i�mil �,i� -1 i 23 I L �. Titre Consent given by Surety:(when required) Project Title Phase 2-Water Reclamation Facility for Sy: the PH Sewer Attorney-in lad Dote You are ordered to perform the following described work upon receipt of an approved copy of this change order: The changes from the original plan were done 1)provide venting to the underground drain station vault and accommodate changes to the odorous air piping at the equalization tank;2)provide Ovivo's changes to the number of anchor bolts per()vivo fabrication submittal;and 3)to extend the fence line on the north side the wastewater treatment plant site. All work materials and measurement to be in accordance with the provisions of the standard specifications and special provisions for the type of construction involved. ORIGINAL CURRENT ESTIMATED ESTIMATED CONTRACT CONTRACT NET CHANGE CONTRACT TOTAL AMOUNT(Intl,9.1%sales tau) AMOUNT(Incl.9.1%sales tax) THIS ORDER(Inca.9.1%sales tax) AFTER CHANGE(Incl.9.1%sales tax) $ 10,020,835.00 $ 10,100,518.94 582,523.59 $ 10,183,042.53 ORIGINAL CURRENT CONTRACT TIME NEW CONTRACT CONTRACTTIME CONTRACT TIME CHANGE[Add/Del) TIME 502 0 N/A N/A APP7RECOMMENDED APPROV COMMENDED / 711 er/2-;-1 .7/45/ Project Manager Dote County Engineer Date iz ....;:: APPA ECOMMENDED APPRO Z ( Approved Telephonically Sic/1 En f ee ervlces Manager �� Date !r Jefferson County Commissioners Date g n g Choir,Jeffe so yf-C JEFFERSON COUNTY Contract No405-2114-0 Sheet 2 of 2 DEPARTMENT OF PUBLIC WORKS Change Date: 7/19/2024 CHANGE ORDER ESTIMATE Order No. 3 ESTIMATED ESTIMATED UNIT UNIT QUANTITY AMOUNT MEASURE PRICE CHANGE CHANGE COP No. DESCRIPTION Additional vent on the drain station and add 004 FRP air line to EQ pump chamber(OCR 003) LS $24,980.69 1 $24,980.69 Additional anchor bolt locations for the Ovivo 005.2 skid mounted units LS $35,795.88 1 $35,795.88 Additional fencing and a new gate north side 011 of WWTP (OCR 006) LS $14,863.75 1 $14,863.75 CO 003 Subtotal $75,640.32 J ESTIMATED NET CHANGE SUBTOTAL: $75,640.32 9.1%Sales Tax $6,883.27 ESTIMATED NET CHANGE TOTAL: $82,523.59 Department of Public Works O Consent Agenda Page 1 of 1 Jefferson County Board of Commissioners Agenda Request To: Board of Commissioners Mark McCauley, County Administrator From: Monte Reinders, P.E., Public Works Director/County Engineer Agenda Date: August 5, 2024 Subject: Change Order No. 3, Phase 2 - Water Reclamation Plant for the Port Hadlock UGA, Project No. 405-2114-0, Commerce Project No. 22-96515-026 Statement of Issue: Change Order No. 3 with Interwest Construction of Burlington, Washington. Analysis/Strategic Goals/Pro's Et Con's: This change order includes the changes to the drain station; anchor bolts for the Ovivo Membrane Bioreactor (MBR) skid mount units; and fencing on the north side of the wastewater treatment plant site. The changes from the original plan were done 1) provide venting to the underground drain station vault and accommodate changes to the odorous air piping at the equalization tank; 2) provide Ovivo's changes to the number of anchor bolts per Ovivo fabrication submittal; and 3) to extend the fence line on the north side the wastewater treatment plant site. Fiscal Impact/Cost Benefit Analysis: The amount for Change Order No. 3 is $82,523.59 (includes 9.1% Washington State Sales Tax). The contract amount will increase from $10,100,518.94 to $10,183,042.53. The project is funded at 100% by the Department of Commerce. Recommendation: Public Works recommends that the Board authorize Change Order No. 3 with Interwest Construction, and return two originals to Public Works for further processing. Department Contact: Samantha Harper, P.E., Project Manager, 385-9175. Reviewed By: 7/4 g - g/lA Mark McCauley ounty Administrator Date