HomeMy WebLinkAboutWSDOT Department of Public Works
O Consent Agenda
Page 1 of I
Jefferson County
Board of Commissioners
Agenda Request
To: Board of Commissioners
Mark McCauley, County Administrator
From: Monte Reinders, P.E., Public Works Director/County Engineer
Agenda Date: August 29, 2024
Subject: WSDOT Local Agency Federal Aid Project Prospectus for
construction funding for Olympic Discovery Trail- Anderson Lake
Connection project, County Project No. 18019893, Road No.
850200
Statement of Issue: As part of administering Federal Grant funding for Public Works
projects, Washington State Department of Transportation (WSDOT) requires the use of
the Local Agency Federal Aid Project Prospectus document to describe Jefferson
County's Olympic Discovery Trail- Anderson Lake Connection project, Project No.
18019893, Road No. 850200.
Analysis/Strategic Goals/Pro's Et Con's: Jefferson County was allocated Federal
funding through the Surface Transportation Block Grant. The proposed trail project
runs from the south end of Larry Scott Trail to the northern boundary of Anderson
Lake State Park. Construction funds will be obligated this year.
Fiscal Impact/Cost Benefit Analysis: The grant amount is $1,519,332. Construction
will be funded at 33% by this grant. The remaining construction funding is from WA
State Recreation and Conservation Office (RCO) WA Wildlife and Recreation-Trails
grant #20-1745.
Recommendation: Public Works recommends that the Board Chair sign the WSDOT
Local Agency Federal Aid Project Prospectus and return to Public Works.
Department Contact: John Fleming, P.E., Project Manager, 360-385-9160.
Reviewed By:
„,,
Mark McCaul , County Administrator Date
Alik
VWashington State Local Agency Federal Aid
A; Department of Transportation g y
Project Prospectus
Prefix Route ( ) Date 8/15/2024
Federal Aid STBGR- DUNS Number 179278197
Project Number
Local Agency 18019893 WSDOT1 Federal Employer 91-6001322
Project Number ` Use Only ) Tax ID Number
Agency CA Agency Federal Program Title
Jefferson County Public Works ✓ Yes ❑ No ✓ 20.205 ❑Other
Project Title Start Latitude N 48.049736 Start Longitude W 122.826253
OlympicDiscoveryTrail-AndersonLkConnection End Latitude N 48.020432 End Longitude W 122.813403
Project Termini From-To Nearest City Name Project Zip Code(+4)
Larry Scott Trail- Anderson Lake St. Park Port Townsend 98368-9366
Begin Mile Post End Mile Post Length of Project Award Type
7.35 10.5 3.15 ✓ Local❑Local Forces❑State❑Railroad
Route ID Begin Mile Point End Mile Point City Number County Number County Name
850200 7.35 10.5 N/A 16 Jefferson
WSDOT Region Legislative District(s) Congressional District(s) Urban Area Number
Olympic Region 24 6 N/A
Total Local Agency Federal Funds Phase Start
Phase Estimated Cost Funding Date
(Nearest Hundred Dollar) (Nearest Hundred Dollar) (Nearest Hundred Dollar) Month Year
P.E. $0 $0 $0 - -
R/W $0 $0 $0 - -
•
Const. $4,621,415 $3,102,083 $1,519,332 10 2024
Total $4,621,415 $3,102,083 $1,519,332
Description of Existing Facility (Existing Design and Present Condition)
Roadway Width Number of Lanes
No existing trail in this location.
Description of Proposed Work
Description of Proposed Work(Attach additional sheet(s)if necessary)
Construction of an Olympic Discovery Trail segment connecting the Larry Scott Trail, through Jefferson
Transit Park &Ride, to Anderson Lake State Park.
Local Agency Contact Person Title Phone
John Fleming PE Engineer 3,Project Manager 360-385-9217
Mailing Address City State Zip Code
623 Sheridan StAVIF ' Kart Townsend WA 98368-2439
It
Project Prospectus Approving Authority
Director of Public Works/County
Title Engineer Datec.04— '
DOT Form 140-101 Page 1
Revised 01/2022 Previous Editions Obsolete
Agency Project Title Date
Jefferson County Public Works OlympicDiscoveryTrail-AndersonLkConnj 8/15/2024
Type of Proposed Work
Project Type(Check all that Apply) Roadway Width Number of Lanes
II New Construction ✓ Path /Trail n 3-R 10' to 16' 1
❑ Reconstruction ❑ Pedestrian / Facilities ❑2-R
❑ Railroad ❑ Parking ❑ Other
❑Bridge
Geometric Design Data
Description Through Route Crossroad
El Principal Arterial ✓ Principal Arterial
Federal ❑ Urban 1-1 Minor Arterial ❑ Urban n Minor Arterial
❑ Collector ❑ Collector
Functional ✓I Rural ✓ Rural
Classification El NHS Major Collector ❑ NHS n Major Collector
✓ Minor Collector n Minor Collector
❑Local Access ❑ Local Access
Terrain ✓ Flat ❑Roll ❑Mountain Flat ❑ Roll ❑Mountain
Posted Speed 35 mph&40 mph 50 mph (35 mph advisory)
Design Speed - -
Existing ADT 2592&2765 5400 to 6000
Design Year ADT - -
• Design Year - -
Design Hourly Volume (DHV) - -
Performance of Work
Preliminary Engineering Will Be Performed By Others Agency
- - % - ok
Construction Will Be Performed By Contract Agency
Contractor 100 % 0 ok
Environmental Classification
n Class I - Environmental Impact Statement (EIS) ✓ Class II -Categorically Excluded (CE)
❑ Project Involves NEPA/SEPA Section 404 ✓ Projects Requiring Documentation
Interagency Agreement (Documented CE)
❑ Class III - Environmental Assessment (EA)
❑ Project Involves NEPA/SEPA Section 404
Interagency Agreements
Environmental Considerations
0.104 acres of wetland will be impacted and mitigated.
DOT Form 140-101 Page 2
Revised 01/2022 Previous Editions Obsolete
Agency Project Title Date
Jefferson County Public Works OlympicDiscoveryTrail-AndersonLkConnj 8/15/2024
Right of Way
-------------
n No Right of Way Needed ✓ Right of Way Needed
*All construction required by the ✓I No Relocation ❑ Relocation Required
contract can be accomplished
within the existing right of way.
Utilities Railroad
❑ No utility work required ✓' No railroad work required
❑All utility work will be completed prior to the start ❑All railroad work will be completed prior to the start of
of the construction contract the construction contract
✓ All utility work will be completed in coordination ❑All the railroad work will be completed in coordination
with the construction contract with the construction contract
Description of Utility Relocation or Adjustments and Existing Major Structures Involved in the Project
Four(4) existing electrical service poles and cables, and two (2) fire hydrants will be relocated by the Public
Utility District#1 of Jefferson County.
FAA Involvement
Is any airport located within 3.2 kilometers (2 miles) of the proposed project? Yes ❑ No
Remarks
This project has been reviewed by the legislative body of the administration agency or agencies, or it's
designee, and is not inconsistent with the agency's comprehensive plan for community development.
Agency Jefferson County Board of Commissioners
Date By
Mayor/Chairperson
DOT Form 140-101 Page 3
Revised 01/2022 Previous Editions Obsolete