HomeMy WebLinkAboutBLD2000-00717 Geotechnical Report Ms. Stephanie Burke SHANNON&WILSON,INC.
November 14, 2000
Page 3
of the bluff. The till consisted of very dense, non-sorted, slightly silty to silty, gravelly sand with
scattered cobbles. The advance outwash appeared to be a very dense sand to sandy silt.
In addition to the very dense till and advance outwash, it appears that slough from the face of the
bluff has accumulated along the toe of the bluff, producing the small, steeply sloping bench
along the toe.
No signs of springs, seeps, damp soils, or other indications of near-surface water were observed
on the property or on the bluff on the adjacent properties.
CONCLUSIONS AND RECOMMENDATIONS
Slope Stability
Geologic hazard maps of the area classify the bluff as unstable. During our site visit, we
observed blocks of hard/very dense till near the base of the bluff that have spalled off the face of
the bluff. The trees that have fallen onto the beach were likely supported by some of these
blocks. Spalling will likely continue in the future. Specifically, vertical cracks were observed in
the till exposed on the bluff. It is likely that as water, roots, freeze/thaw and other forces extend
and widen these cracks, portions of the bluff will spall off in the future.
Based on our observations of the site, it appears that the unstable soils are primarily blocks that
spall off the near-vertical bluff face. While there may be some risk of deep-seated slope
movement at the site (i.e., failure through several tens of feet of the very dense glacial soils
beneath the site), it is our opinion that this risk is relatively low because evidence of deep-seated
movement was not observed during our site visit.
With enough time, the accumulation of spalled soils (or slough) at the base of the bluff and
continued weathering and erosion of the glacially overridden soil beneath the bluff would result
in a flatter, more stable slope. However, wave erosion at the toe of the bluff does not allow the
slough to accumulate at the toe of the slope, but maintains the slope in an over-steepened
condition. Consequently, spalling of the bluff face should be expected to continue in the future.
Please note that there is some risk of future instability (shallow or deep-seated) present on all
hillsides, which the owner must be prepared to accept. Such instability could occur because of
future water line breaks/leaks, uncontrolled drainage, unwise development in adjacent areas, or
2 1-1-0921 5-001-L 1.DOCIWP/EET 21-1-09215-001
Ms. Stephanie Burke SHANNON 6WILSON,INC.
November 14, 2000
Page 4
other actions or events on a slope that may cause sliding. The following section provides further
discussion of risk reduction measures that may be effective at this site. Provided that the risk
reduction measures discussed in this letter are implemented, it is our opinion that the proposed
development will not adversely impact the stability of the adjacent properties.
Measures to Reduce the Risk Posed by Slope Movement
In general, the risk of soil movement on a slope can be reduced by not over-steepening the slope
(e.g., avoiding excavation at the toe of the slope); not increasing the weight on the slope (e.g.,
avoiding placement of yard debris or fill at the crest of the slope); maintaining the slope as dry as
possible (e.g., routing roof downspouts and yard drains to the base of the slope or storm drain
system, minimizing the amount of surface water that could flow down the face of the slope); and
maintaining a vegetative cover on or above the slope. In addition, measures that can be taken to
reduce or minimize the rate of wave erosion at the toe of the slope (e.g., construction of a
seawall, not removing large wood debris or driftwood near the top of the beach) will decrease the
rate at which the slope erodes.
Building Set Back
The measures discussed above may reduce the risk of soil movement on a slope. One of
the most cost-effective measures to reduce the impact of slope movement is to provide an
adequate building setback. An appropriate building setback is a function of the rate of slope
regression, the design life of the structure, and the risk the owner of the structure is willing to
assume. The regression rate for this specific slope is unknown; regression rates measured
elsewhere in the Puget Sound area are on the order of a few inches to one foot per year. The size
(up to 1 ] feet in diameter) of roots and tree-trunks that extend part way down over the face of
the bluff would tend to indicate a relatively slow rate of regression, probably on the order of a
few inches per year. In our opinion, a minimum building set-back equal to the height of the
slope (i.e., 35 feet) would be adequate for this site. Greater risk reduction can be achieved with
larger building set-backs, such as 1.5 or 2 times the height of the slope.
The actual rate of slope regression will likely vary from year to year (e.g., some years no
noticeable regression may occur, while in other years the slope may regress by several feet due
to slope movements). By implementing the measures outlined in this letter for reducing the risk
of slope movement, the rate of slope regression may also be reduced.
2 1-1-0921 5-001-LI.DOC/W P/EET 21-1-09215-001
• Ms. Stephanie Burke November 14, 2000 SHANNON&WILSON,INC.
Page 5
I
Drainage
111 In general, reducing the amount of water entering and discharging onto the bluff can
reduce the risk of slope movement. Drains should be constructed and maintained to collect water
from impermeable surfaces on the property (e.g., roof, decks, patios, and driveways) and directed
to a suitable discharge point (e.g., bottom of the bluff). If water is discharged to the toe of the
bluff, we recommend that it be conveyed in a flexible tightline on the surface of the bluff and
periodically inspected and maintained. The tightline can be supported by steel stakes driven into
the soils on the crest of the bluff. Stainless or galvanized steel cable and clamps can be used to
attach the tightline to stakes. Alternatively, the tightline could be supported on the wooden
stairway under construction. Splices in the tightline on the bluff should be avoided. If tightline
splices occur on the bluff, the splice should be supported and reinforced using stainless or
galvanized steel cable attached to the tightline both above and below the splice.
The water collected in the tightline should be discharged as close to the beach elevation
as allowable. This is typically at or immediately above the high water elevation, and could be on
top of the small steep slope at the bottom of the bluff, in an area behind some of the larger
driftwood. An energy dissipater should be located at the discharge point. The energy dissipater
may be constructed by connecting 3 feet (total width) of perforated drain pipe to form a "T" at
the end of the tight line. The "T" should be located on a minimum 12-inch-thick layer of 6-inch
or larger diameter cobbles or quarry spalls that extend a minimum of 3 feet beyond the ends of
the perforated pipe that forms the "T." The "T" may be covered with cobbles or quarry spalls to
help secure and hide the "T." It may be necessary to add rock to the energy dissipater from time
to time due to erosion of the small slope.
Based on our understanding of the limited, single-residence development
nt of this property
and the relatively well-drained nature of the soils that underlie the upland portion of the site, it is
our opinion that the anticipated discharge of roof and footing drains as recommended above will
not significantly affect the drainage conditions on the adjacent properties from pre-development
conditions. Imperrrleable surfaces surrounding the residence (e.g., paved drives) should be
minimized to reduce potential changes in the existing site drainage characteristics and impacts on
adjacent sites.
I
2 1-1-092 1 5-001-L1.DOC/WP/EET 21-1-09215-001
I
Ms. Stephanie Burke November 14, 2000 SHANNON&WILSON,INC.
Page 6
I
Vegetation
Maintaining a healthy vegetative cover above the bluff can reduce erosion and the rate of
slope regression. In general, native vegetation should be used on the top of the bluff to eliminate
1111 the need for irrigation and wetting the soils on or near the bluff. A healthy vegetative cover may
include large, healthy trees. Unhealthy trees, snags or other trees with a weak root system could
be removed or limbed to reduce the risk of potential erosion and slope movement caused by
potential uprooting during heavy winds. If trees are cut from the slope, the stumps should not be
removed and the area around the stump should be vegetated. A professional landscaper,
Ulandscape architect, arborist, or other qualified professional should be consulted in assessing the
health of the trees and vegetation on the slope and vegetation that may be planted.
Erosion Hazard
We note that according to published USDA soil maps, surficial soils on the upland portion of the
1111 site are classified as Whidbey gravelly sandy loam D on 15 to 30 percent slopes. The USDA
maps indicate that these soils have moderate erosion hazard. The soil maps do not classify the
111 soils on the bluff. It is anticipated that the development on the upland portion of the site will not
significantly affect soil erosion and associated hazard on the site provided the recommendations
in this letter are followed and prudent construction practices with respect to erosion are used.
LIMITATIONS
The conclusions in this letter are based on site conditions visually observed during our site
reconnaissance and inferred from published geologic, topographic, and hazard maps, and assume
that observed conditions are representative of the subsurface conditions throughout the site; i.e.,
the subsurface conditions are not significantly different from those inferred from the site
reconnaissance or indicated on geologic maps. During subsequent site activities (e.g.,
construction), if subsurface conditions different from those inferred in this letter are observed or
appear to be present, we should be advised at once so that we can review those conditions and
reconsider our conclusions where necessary.
Within the limitations of scope, schedule, and budget, the conclusions presented in this letter
were prepared in accordance with generally accepted geologic engineering principles and
U practices in this area at the time this letter was prepared. We make no other warranty, either
express or implied.
2 1-1-092 1 5-001-L1.DOC/WP/EET 21-1-09215-001
I
Ms. Stephanie Burke SHANNON FiWILSON,INC.
November 14, 2000
Page 7
111
This letter was prepared for the use of Ms. Burke in the evaluation of the stability of this site.
With respect to possible future construction, it should be made available for information on
factual data only and not as a warranty of subsurface conditions, such as those interpreted from
the site visit and discussion of geologic conditions included in this letter.
Please note that the scope of our services did not include any environmental assessment or
evaluation regarding the presence or absence of wetlands or hazardous or toxic material in the
soil, surface water, groundwater, or air, on or below or around this site. We are able to provide
these services and would be pleased to discuss these with you if the need arises.
Shannon & Wilson has prepared the attached, "Important Information About Your Geotechnical
Report," to assist you in understanding the use and limitations of our report.
We appreciate the opportunity to provide geologic services to you, and are available to answer
any questions regarding our observations and conclusions contained in this letter.
Sincerely,
SHANNON WILSON, INC.
NI D
RoF\J
c J OREGON � \
/I-I PrRKI" \
Ne. 65 ll A
William J. Perkins, R.P.G.
Principal Engineering Geologist
WJP:GJB:wjp
Enclosures: Figure 1 —Vicinity Map
Figure 2—Site Plan
Figure 3 —Generalized Profile
Important Information About Your Geotechnical Report
c: Michael Anderson, Tillman Engineering
21-1-09215-001-LI.DOC/WP/EET 21-1-09215-001