JEFFCOM 9-1-1 Improvements Change Order Requests No. 10, 11, U and 13
STATEMENT OF ISSUE: Approval and execution of Change Order Request (COR) No. 10 in the amount
of $6,167.00, COR No. 11 in the amount of$10,469.00, COR No. 12 in the amount of$11,165.00 and COR
No. 13 in the amount of$23,132.00, all for BnchAuan Gen~ Contracting Company (Conttactor).
ANALYSIS: On Janumy 25, 2010, the Board of County CommillSioners approved and executed a contract
with Buchanan General Contracting Company, P.O. Box 40069, Bellevue, W A 98015 for the construction of
the Je~om 9-1-1 Radio System Improvement Project. Construction started at the South (Coyle) and Maynard
Peak sites on February 8. Work began at the Green Mountain site the fust week ofMa.rch. The following
CORs are essential for the completion of construction at the Maynard Peak, Green Mountain and Port
Townsend sites. Change Order Request No. 10, 11, 12 and 13 are attached for your approval and execution.
COR No. 10 is for an additional 'ice bridge' (a s1ructUre to support and protect the microwave guides and
cabling from the tower to the equipment s1ructUre) to be constructed at the Maynard Peak site. The original
design and bid included one 'ice bridge' and a second one is required.
COR No. 11 is for an additional 'ice bridge' to be constructed at the Green Mountain site. The original design
and bid included one 'ice bridge' to the tower but it needs to be extended to the vertica1'cable ladder' which
carries the cabling up the tower.
COR No. 12 is for the revised propane fuel tank f01mdl!tiou slab and protective bollards at the Green Mountain
site. COR No.3 deleted the original designed fuel tank enclosure included in the bid but didn't include these
costs for the revised design and construction.
COR No. 13 is for construction of the access road and preparation for the Port Townsend water reservoir site
for access by the geotechnical engineers for soil testing which is required for the design and permitting.
These CORs were approved by the Je~m Administrative Board on June 24, 2010.
FISCAL IMPACT: Funds will be provided by the JeffCom Enhancement Fund 121 which was funded by a
2007 bond issue. The total amount of the original contract with sales tax is $364,728.08. Change Order
Requests No.1 through 9 increased the current approved cost to $399,798.08. The total ofCORs 10, 11, 12
and 13 is $50,933.00 bringing the new total to $450,731.08. The total ofCORs 1 through 13 is $86,003.00 or
23.58% of the original contract. Sufficient funds are available.
RECOMMENDATION: Move to approve and execute Change Order Request No. 10, II, 12 and 13 to the
JefK:om 911 Radio System Improvement Contraet with B1IChanan General Con1Iacting Company.
~
A 'sttmQr ~
bh;;o
Date
JEFFCOM 9-1-1 Radio System Improvements
CHANGE ORDER REQUEST No. 10, 11, 12 and 13
:
CONTRACTOR Buchanan General Contracting Company
:
CONTACT PERSON Terry Buchanan
:
ADDRESS P.O. Box 40069, Bellevue, WA 98015
:
TELEPHONE NUMBER (425) 462-1326
:
E-MAIL terry@buchanangc.com
:
DEPARTMENT JEFFCOM 9-1-1
:
JEFFCOM 9-1-1 CONTACT Sheriff Anthony Hernandez (by Larry Southwick)
:
TELEPHONE NUMBER (360) 385-3831 (Southwick 360-379-2878)
:
PROJECT JEFFCOM 9-1-1 Radio System Improvement Project
:
AMOUNT $50,933.00
:
FUND SOURCE Encumbered JEFFCOM 9-1-1 Enhancement Funds
:
CONTRACT DURATION 90 working days from February 8, 2010
June 1, 2010
Little Construction
2009 4th Street
Port Townsend, WA 98368
Attention: Alex Little
Reference: JEFFCOMM 911
CE10 – Additional Ice Bridge – Maynard Peak
Dear Alex,
We are pleased to submit a lump sum quotation of $6,167.00 to provide all of the labor,
material, equipment and supervision to install additional ice bridg at the Maynard Peak site
per the provided design. A copy of our breakdown is attached.
Please issue an authorization to proceed with this additional work. Thank you.
Very Truly Yours,
Buchanan General Contracting Company
Terry Buchanan
Project Manager
Cc: Larry Southwick
PO Box 40069 Bellevue, WA 98015
phone 425 462-1326fax 425 462-9468 www.buchanangc.com
BUCHAGC 159CF
Buchanan General Contracting Co.Estimator:Rod
Jeffcom 911 - Maynard PeakPrint date:6/1/10
CE10 - Additional Ice Bridge - Maynard Peak
BGC LaborMaterialSubcontractorTotalNotes
CodeDescriptionQuantityUnitTotalUnitTotalUnitTotalCost
GENERAL CONDITIONS
Superintendent12hr49.635960.0000.000596
As built drawings1ls0.0000.00035.003535
Telephone0.10mo0.000225.00230.00023
Subsistance Superintendent2da0.00010.00200.00020tolls
Subsistance Craft3da0.00025.00750.00075fuel & tolls
Travel trucks1.0ea0.00075.00750.00075
Construction equipment0.10mo0.000480.00480.00048
Pick up truck0.10mo0.000615.00620.00062
Small tools0.10mo0.000480.00480.00048
Fuel and maintenance0.10mo0.0001275.001280.000128
Fuel adjustment0.10mo0.0000.0000.0000none
SUBTOTAL GENERAL CONDITIONS596478351108
Furnish & Install Additional Ice Bridge
pick-up & deliver components3hr15.00450.0000.00045
auger bridge posts 36"x12"1ea30.003080.00800.000110
buy & set 3 1/2" post & cap1ea15.0015143.001430.000158B237
buy, tie & set rebar @ 20# ea20#0.75150.0311.202440
hand mix sack concrete @ post4sk7.50306.50260.00056
buy & set 3 1/2" footed post & cap1ea15.0015148.001480.000163B279
parabolts @ footed post4ea3.00123.50140.00026
buy & set 24" grip strut20lf3.006028.005600.000620
arm over brackets2ea15.003055.001100.000140B1211
coax support assembly @ 3' oc 7ea15.0010550.003500.000455B1890
Grounding @ New Ice Bridge
hand excavate to ground ring1hr15.00150.0000.00015
ground added posts2ea15.003040.00800.000110
added ground buss bar1ea30.0030125.001250.000155
tie new buss bar into ground ring1ea30.003030.00300.00060
1,0582,144593,261
Labor Adjustment208.93%96500965
Labor Taxes31.65%64000640
Total Labor, Material, & Sub2,6632,144594,866
Overhead & Fee13.50%657
Sub Total5,523
B&O, & Insurance3.01%166
Sub Total5,689
WSST8.40%478
Total Bid$6,167
Copy of CE10 - Additional Ice Bridge Maynard PeakPage 1
June 1, 2010
Little Construction
2009 4th Street
Port Townsend, WA 98368
Attention: Alex Little
Reference: JEFFCOMM 911
CE11 – Additional Ice Bridge – Green Mountain
Dear Alex,
We are pleased to submit a lump sum quotation of $10,469.00 to provide all of the labor,
material, equipment and supervision to install additional ice bridg at the Green Mountain site
per the provided design. A copy of our breakdown is attached.
Please issue an authorization to proceed with this additional work. Thank you.
Very Truly Yours,
Buchanan General Contracting Company
Terry Buchanan
Project Manager
Cc: Larry Southwick
PO Box 40069 Bellevue, WA 98015
phone 425 462-1326fax 425 462-9468 www.buchanangc.com
BUCHAGC 159CF
Buchanan General Contracting Co.Estimator:Rod
Jeffcom 911 - Green MountainPrint date:6/1/10
CE11 - Additional Ice Bridge, Green Moutain
BGC LaborMaterialSubcontractorTotalNotes
CodeDescriptionQuantityUnitTotalUnitTotalUnitTotalCost
GENERAL CONDITIONS
Superintendent16hr49.637940.0000.000794
As built drawings1ls0.0000.00035.003535
Telephone0.10mo0.000225.00230.00023
Subsistance Superintendent2da0.00010.00200.00020tolls
Subsistance Craft6da0.00025.001500.000150fuel & tolls
Travel trucks1.0ea0.00075.00750.00075
Construction equipment0.10mo0.000480.00480.00048
Pick up truck0.10mo0.000615.00620.00062
Small tools0.10mo0.000480.00480.00048
Fuel and maintenance0.10mo0.0001275.001280.000128
Fuel adjustment0.10mo0.0000.0000.0000none
SUBTOTAL GENERAL CONDITIONS794553351382
Furnish & Install Additional Ice Bridge
pick-up & deliver components3hr15.00450.0000.00045
hand excavate post pads 3'x2'x2'4ea30.001200.0000.000120
2x4 forms @ top40lf1.50601.65660126
buy, tie & set rebar @ 20# ea80#0.75600.0321.2096158
buy & place concrete post piers1.5cy30.0045143.00215150.00225485short load
buy & set 3 1/2" footed post & cap4ea15.0060148.005920.000652B279
parabolts @ footed post16ea3.00483.50560.000104
buy & set 24" grip strut30lf3.009028.008400.000930
arm over brackets4ea15.006055.002200.000280B1211
coax support assembly @ 3' oc 9ea15.0013550.004500.000585B1890
Grounding @ New Ice Bridge
hand excavate to ground ring2hr15.00300.0000.00030
ground added posts4ea15.006040.001600.000220
added ground buss bar1ea30.0030125.001250.000155
tie new buss bar into ground ring1ea30.003030.00300.00060
1,6673,3083565,331
Labor Adjustment208.93%1,824001,824
Labor Taxes31.65%1,105001,105
Total Labor, Material, & Sub4,5963,3083568,260
Overhead & Fee13.50%1,115
Sub Total9,376
B&O, & Insurance3.01%282
Sub Total9,658
WSST8.40%811
Total Bid$10,469
Copy of CE11 - Additional Ice Bridge Green MountainP, a0g6e-0 11-10
June 1, 2010
Little Construction
2009 4th Street
Port Townsend, WA 98368
Attention: Alex Little
Reference: JEFFCOMM 911
CE12 – Fuel Tanks Slab and Bollards – Green Mountain
Dear Alex,
We are pleased to submit a lump sum quotation of $11,165.00 to provide all of the labor,
material, equipment and supervision to install the revised fuel tank slab at the Green
Mountain site after we credited back the original slab in Change Estimate Three. A copy of
our breakdown is attached.
Please issue an authorization to proceed with this additional work. Thank you.
Very Truly Yours,
Buchanan General Contracting Company
Terry Buchanan
Project Manager
Cc: Larry Southwick
PO Box 40069 Bellevue, WA 98015
phone 425 462-1326fax 425 462-9468 www.buchanangc.com
BUCHAGC 159CF
Buchanan General Contracting Co.Estimator:Rod
Jeffcom 911 - Green MountainPrint date:6/1/10
CE12 - Fuel Tank Slab and Bollards, Green Moutain
BGC LaborMaterialSubcontractorTotalNotes
CodeDescriptionQuantityUnitTotalUnitTotalUnitTotalCost
GENERAL CONDITIONS
Superintendent24hr49.631,1910.0000.0001,191
As built drawings1ls0.0000.00035.003535
Telephone0.15mo0.000225.00340.00034
Subsistance Superintendent3da0.00010.00300.00030tolls
Subsistance Craft7da0.00025.001750.000175fuel & tolls
Travel trucks2.0ea0.00075.001500.000150
Construction equipment0.15mo0.000480.00720.00072
Pick up truck0.15mo0.000615.00920.00092
Small tools0.15mo0.000480.00720.00072
Fuel and maintenance0.15mo0.0001275.001910.000191
Fuel adjustment0.15mo0.0000.0000.0000none
SUBTOTAL GENERAL CONDITIONS1191816352042
ADD PROPANE TANK SLAB - 6'x18'
1/0hand excavate thickened edge 3cy22.50680.0000.00068
1/2load, haul & dispose of debris4cy3.75156.50260.00041
fine grade & compact 108sf0.66710.0000.00071
24'' edge forms - 48'48sf1.80861.75840.000170
buy & place rebar160#0.28450.0350.65104154
3/4" champher strip53lf0.45240.35190.00042
screeds108sf0.12130.12130.00026
buy & place concrete 6"6cy15.009087.005220.000612
finish concrete108sf0.45490.0000.00049
cure & protect108sf0.10110.0890.00019
BUY & PLACE 6" PIPE BOLLARDS
pick-up & deliver bollards3hr15.00450.0000.00045
hand excavate for bollards5ea30.001500.0000.000150
1/2load, haul & dispose of debris2cy3.7586.50130.00021
buy & place 6" galvanized bollards5ea30.00150195.009750.0001,125
buy & place concrete @ bollards2.5cy30.007587.002180.000293
Grounding @ Bollards
hand excavate to ground ring4hr15.00600.0000.00060
ground pipe bollards5ea15.007540.002000.000275
2,2252,8991395,263
Labor Adjustment208.93%2,160002,160
Labor Taxes31.65%1,388001,388
Total Labor, Material, & Sub5,7722,8991398,810
Overhead & Fee13.50%1,189
Sub Total9,999
B&O, & Insurance3.01%301
Sub Total10,300
Copy of CE12 - Fuel Tank Slab Green Mountain, 06-0P1a-g1e0 1
Buchanan General Contracting Co.Estimator:Dennis
Jeffcom 911 - Green MountainRevsion 1Print date:6/17/10
CE13 - Geotech Access, Opt #2, Pt Townsend
BGC LaborMaterialSubcontractorTotalNotes
CodeDescriptionQuantityUnitTotalUnitTotalUnitTotalCost
General Conditions
SUPERINTENDENT
Superintendent24hr49.631,1910.0000.0001,191
Meetings & Reporting4hr49.631990.0000.000199
Site Walks2hr49.63990.0000.00099
Telephone0.37mo0.000225.00830.00083
Subsistance Superintendent8da0.00010.00800.00080toles
Subsistance Craft8da0.00025.002000.000200fuel & toles
Travel trucks2ea0.00075.001500.000150
Job office1ls0.00090.00900.00090
Sanitary convenience1ls0.000130.001300.000130
Local yard (composite rate)2hr40.038032.50650.000145
Disposal1ea80.068097.5098115.00115293
Mobilize & Demobilize2hr40.038032.50650.000145
Safety2hr49.639925.00500.000149
Construction equipment0.37mo0.000295.001090.000109
Pick up truck0.37mo0.000650.002410.000241
Tool sharpening1ls0.0000.0000.0000
Job photos1ls0.00050.00500.00050
Small tools0.37mo0.000295.001090.000109
Fuel and maintenance0.37mo0.0001000.003700.000370
Fuel adjustment0.37mo0.0000.0000.0000none
Locates4hr0.0000.000125.00500500
Foreman (carpenter)4hr48.631950.0000.000195
Survey and Engineer Site1ls0.00080.00800.00080
SUBTOTAL GENERAL CONDITIONS202319706154607
EQUIPMENT1s/c0.0000.0000.0000
Mob/demob equipment1ls0.0000.000430.00430430
SITEWORK1s/c0.0000.0000.0000
Access Road - 15'x30' w/flares1s/c0.0000.0000.0000
580 Backhoe 7hr0.0000.000125.00875875
10cy Dump2hr0.0000.00090.00180180
2/0clear & grub 50sy0.60300.0000.00030
1/2load, haul & dispose10cy1.50158.00800.00095
2/0rough grade & compact50sy0.60300.0000.00030
compactor0.5da30.0015115.00580.00073
filter fabric675sf0.09570.151010.000159
2/0import & place gravel @ 6"10cy3.003023.452350.000265
finish grade45sy0.67300.0000.00030
plate compactor - clean-up0.5da30.0015115.00580.00073
Compound - 50'x12' + 30'x30'1s/c0.0000.0000.0000
580 Backhoe 18hr0.0000.000125.0022502,250
10cy Dump6hr0.0000.00090.00540540
cut down trees & heavy brush8hr15.001200.0000.000120
Copy of CE13 - Geotech Access Opt #2 Pt TownsendP, a0g6e- 117-10
Buchanan General Contracting Co.Estimator:Dennis
Jeffcom 911 - Green MountainRevsion 1Print date:6/17/10
CE13 - Geotech Access, Opt #2, Pt Townsend
BGC LaborMaterialSubcontractorTotalNotes
CodeDescriptionQuantityUnitTotalUnitTotalUnitTotalCost
CHAIN LINK FENCE - 6'CLF1s/c0.0000.0001158.0011581,158viking
580 Backhoe 1hr0.0000.000125.00125125john
10cy Dump0hr0.0000.0000.0000
open existing fence15lf2.00300.0000.00030
1/0pull fence posts2ea0.0000.0000.0000
load, haul & dispose of debris2cy7.501510.002030.006095
install to permanent gate posts2ea0.0000.0000.0000
12' double gate1ea0.0000.0000.0000
3,3144,1046,35013,769
Labor Adjustment198.67%2,566002,566
Labor Taxes32.61%1,918001,918
Total Labor, Material, & Sub7,7984,1046,35018,252
Overhead & Fee13.50%2,464
Sub Total20,716
B&O, & Insurance3.01%624
Sub Total21,339
WSST8.40%1,793
Total Bid$23,132