HomeMy WebLinkAboutCONSENT Change Order 8 re Phase 2 Water Department of Public Works
O Consent Agenda
Page 1 of 1
Jefferson County
Board of Commissioners
Agenda Request
To: Board of Commissioners
Mark McCauley, County Administrator
From: Monte Reinders, P.E., Public Works Director/County Engineer
Agenda Date: May 27, 2025
Subject: Change Order No. 8, Phase 2 - Water Reclamation Plant for the
Port Hadlock UGA, Project No. 405-2114-0, Commerce Project No.
22-96515-026
Statement of Issue: Change Order No. 8 with Interwest Construction of Burlington,
Washington.
Analysis/Strategic Goals/Pro's Et Con's: This change order modifies the original plan
in the following ways: 1) Plumbing changes in Admin and Chemical Buildings; and 2)
electrical vault risers to bring vault lids to revised pavement grade; 3) additional seed
sludge volume needed to "prime" the wastewater treatment plant for system start
up.
Fiscal Impact/Cost Benefit Analysis: The amount for Change Order No. 8 is
$27,465.54 (includes 9.2% Washington State Sales Tax). The contract amount will
increase from $ $10,477,011.02 to $10,504,476.56. The project is funded at 100% by
the Department of Commerce.
Recommendation: Public Works recommends that the Board authorize Change Order
No. 8 with Interwest Construction, and return two originals to Public Works for further
processing.
Department Contact: Samantha Harper, P.E., Project Manager, 385-9175.
Reviewed B
55
Mark McCauley," ounty Administrator Date(
JEFFERSON COUNTY
Sheet 1 of 2 DEPARTMENT OF PUBLIC WORKS Change S
Date: 5/13/2025 CHANGE ORDER order No.
Ordered by County Engineer under terms of
❑X Article 9 and 11 of the General and Supplemental Conditions 405-2.1 f 8•I)
Contract No.
Change proposed by Contractor To:
Interwest Construction
Endor ed by: 4575 Fey Rd
L In,_�CA y_;- ,, Ko'-C Port Angeles,WA 98363
1/11ki C tractor Firm Nome
Slg ure Dote
17(fe
Consent given by Surety:(when required) Project Title Phase 2-Water
Reclamation Facility for
By: the PH Sewer
Attorney-in-loci Dote
You are ordered to perform the following described work upon receipt of an approved copy of this change order:
The changes for this change order were 1)plumbing changes in Admin and Chemical Buildings due to a change in the
chemical system per COP 30;2)installation of vault risers to meet pavement grades per COP 31;and 3)additional
seed sludge for start up.
i
i
All work materials and measurement to be in accordance with the provisions of the standard specifications and
special provisions for the type of construction involved.
ORIGINAL CURRENT ESTIMATED ESTIMATED
CONTRACT CONTRACT NET CHANGE CONTRACT TOTAL
AMOUNT(incl.9.1%Sales tax) AMOUNT(Intl.9.1%sales tax) THIS ORDER(incl.9.2%sales tax) AFTER CHANGE(Intl.9.1%sales tax)
$ 10,020,835.00 5 10,477,011.02 $27,465.54 $ 10,504,476.56
ORIGINAL CURRENT CONTRACT TIME NEW CONTRACT
CONTRACT TIME CONTRACT TIME CHANGE(Add/Del) TIME
502 D N/A N/A
APPROVAL RECOMMENDED APPR VAL REC MENDED
� �3I� S'• 1i• zi
Profec Manager Dote County Engineer Dote
APPROVAL RECOMMENDED APPROVED
1101�- o
Engineering Services Manager Dote Choir,Jefferson County Commissioners Dote
JEFFERSON COUNTY 7 Contract No 405-2114-0
Sheet 2 of 2 DEPARTMENT OF PUBLIC WORKS
Change
Date: 5/13/2025 CHANGE ORDER ESTIMATE Order No. 8
ESTIMATED ESTIMATED
UNIT UNIT QUANTITY AMOUNT
MEASURE PRICE CHANGE CHANGE
COP No. DESCRIPTION
30 Admin/Chemical Building Plumbing Changes LS $8,981.82 1 $8,981.82
Added Vault Risers to Meet New Pavment
31 Grades LS $13,606.72 1 $13,606.72
33 Additional Seed Sludge LS $2,563.05 1 $2,563.05
4
CO 08 Subtotal $25,151.59
ESTIMATED NET CHANGE SUBTOTAL: $25,151.59
9.2%Sales Tax $2,313.95
ESTIMATED NET CHANGE TOTAL: $27,465.54